Skip to content

Ryze By Aum construction progress

The registered completion date for Ryze By Aum in Warsan First Development is June 2028. At the last site inspection, in August 2026, it was 0.1% built. The developer is Aum Real Estate Development.

0.1%

Built, at the site inspection of 10 August 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
May 3087
Construction started
December 2025
First registered
December 2025
Developer
Aum Real Estate Development
Units
93
Escrow bank
Dubai Islamic Bank
Name in Arabic
رايز من اوم
Project number
4021
Site inspections
3

Schedule

Between August 2025 and August 2026 the site added about 0.0 points a month. At that rate it would finish around May 3087, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 August 2026

0.1%+0.0 pts

  • Ryze By Aum construction site, inspection photo 1, 10 August 2026
  • Ryze By Aum construction site, inspection photo 2, 10 August 2026
  • Ryze By Aum construction site, inspection photo 3, 10 August 2026
  • Ryze By Aum construction site, inspection photo 4, 10 August 2026

8 April 2026

0%+0.0 pts

  • Ryze By Aum construction site, inspection photo 1, 8 April 2026
  • Ryze By Aum construction site, inspection photo 2, 8 April 2026

26 August 2025

0%

  • Ryze By Aum construction site, inspection photo 1, 26 August 2025
  • Ryze By Aum construction site, inspection photo 2, 26 August 2025

All 8 site photos, by inspection date

Context

Warsan First Development has 3 projects under construction, 2.6% built on average.

Own a unit in Ryze By Aum?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ryze By Aum handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 3087. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ryze By Aum?
Ryze By Aum was 0.1% built at the site inspection on 10 August 2026. The site has been inspected 3 times since August 2025. The Land Department took 8 site photos at its inspections.
Is Ryze By Aum delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Ryze By Aum?
The registered developer is Aum Real Estate Development.
Which bank holds the escrow account for Ryze By Aum?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.