Riwa construction photos
37 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Riwa was built on the day of each visit.
20 July 202613% built
30 April 20266.5% built
23 January 20263.3% built
23 October 20250.2% built
31 July 20250% built
7 May 20250% built
12 February 20250% built
28 March 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.