Madinat Jumeriah Living - Phase 2 construction progress

The register lists Madinat Jumeriah Living - Phase 2 in Um Suqaim Third as complete, with a registered completion date of December 2022. Its last site inspection on record was in February 2022. The developer is Jumeirah Hills Development.

100%

Built, at the site inspection of 1 February 2022

Construction complete

Registered completion date
December 2022
Construction started
February 2019
First registered
December 2018
Units
364
Escrow bank
Emirates NBD
Name in Arabic
مدينة جميرا ليفينج - المرحله 2
Project number
2116
Site inspections
6

Schedule

The register lists Madinat Jumeriah Living - Phase 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 February 2022

100%+14 pts

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 1 February 2022
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 1 February 2022
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 1 February 2022
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 1 February 2022

28 June 2021

86%+34 pts

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 28 June 2021
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 28 June 2021
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 28 June 2021
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 28 June 2021

20 December 2020

52%+30 pts

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 20 December 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 20 December 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 20 December 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 20 December 2020

16 June 2020

22%+11 pts

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 16 June 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 16 June 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 16 June 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 16 June 2020

26 February 2020

11%+11 pts

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 26 February 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 26 February 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 26 February 2020
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 26 February 2020

11 July 2019

0.4%

  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 1, 11 July 2019
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 2, 11 July 2019
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 3, 11 July 2019
  • Madinat Jumeriah Living - Phase 2 construction site, inspection photo 4, 11 July 2019

All 62 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Madinat Jumeriah Living - Phase 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Madinat Jumeriah Living - Phase 2 handover date?
Construction of Madinat Jumeriah Living - Phase 2 is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Madinat Jumeriah Living - Phase 2?
Madinat Jumeriah Living - Phase 2 was 100% built at the site inspection on 1 February 2022. The site has been inspected 6 times since July 2019. The Land Department took 62 site photos at its inspections.
Is Madinat Jumeriah Living - Phase 2 delayed?
The register lists construction as complete.
Who is building Madinat Jumeriah Living - Phase 2?
The registered developer is Jumeirah Hills Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Madinat Jumeriah Living - Phase 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.