Lamaa construction progress

The register lists Lamaa in Um Suqaim Third as complete, with a registered completion date of January 2026. Its last site inspection on record was in July 2026. The developer is Jumeirah Hills Development.

100%

Built, at the site inspection of 14 July 2026

Construction complete

Registered completion date
January 2026
Construction started
December 2022
First registered
October 2022
Units
372
Escrow bank
Commercial Bank of Dubai
Name in Arabic
لـمـــاع
Project number
2471
Site inspections
11

Schedule

The register lists Lamaa as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

100%+7.9 pts

  • Lamaa construction site, inspection photo 1, 14 July 2026
  • Lamaa construction site, inspection photo 2, 14 July 2026
  • Lamaa construction site, inspection photo 3, 14 July 2026
  • Lamaa construction site, inspection photo 4, 14 July 2026

20 May 2026

92%+7.6 pts

  • Lamaa construction site, inspection photo 1, 20 May 2026
  • Lamaa construction site, inspection photo 2, 20 May 2026
  • Lamaa construction site, inspection photo 3, 20 May 2026
  • Lamaa construction site, inspection photo 4, 20 May 2026

2 February 2026

84%+8.6 pts

  • Lamaa construction site, inspection photo 1, 2 February 2026
  • Lamaa construction site, inspection photo 2, 2 February 2026
  • Lamaa construction site, inspection photo 3, 2 February 2026
  • Lamaa construction site, inspection photo 4, 2 February 2026

22 October 2025

76%+9.4 pts

  • Lamaa construction site, inspection photo 1, 22 October 2025
  • Lamaa construction site, inspection photo 2, 22 October 2025
  • Lamaa construction site, inspection photo 3, 22 October 2025
  • Lamaa construction site, inspection photo 4, 22 October 2025

28 July 2025

66%+6.2 pts

  • Lamaa construction site, inspection photo 1, 28 July 2025
  • Lamaa construction site, inspection photo 2, 28 July 2025
  • Lamaa construction site, inspection photo 3, 28 July 2025
  • Lamaa construction site, inspection photo 4, 28 July 2025

29 April 2025

60%+19 pts

  • Lamaa construction site, inspection photo 1, 29 April 2025
  • Lamaa construction site, inspection photo 2, 29 April 2025
  • Lamaa construction site, inspection photo 3, 29 April 2025
  • Lamaa construction site, inspection photo 4, 29 April 2025

15 January 2025

41%+16 pts

  • Lamaa construction site, inspection photo 1, 15 January 2025
  • Lamaa construction site, inspection photo 2, 15 January 2025
  • Lamaa construction site, inspection photo 3, 15 January 2025
  • Lamaa construction site, inspection photo 4, 15 January 2025

23 September 2024

25%+22 pts

  • Lamaa construction site, inspection photo 1, 23 September 2024
  • Lamaa construction site, inspection photo 2, 23 September 2024
  • Lamaa construction site, inspection photo 3, 23 September 2024
  • Lamaa construction site, inspection photo 4, 23 September 2024

20 March 2024

2.9%+2.9 pts

  • Lamaa construction site, inspection photo 1, 20 March 2024
  • Lamaa construction site, inspection photo 2, 20 March 2024

4 September 2023

0%

  • Lamaa construction site, inspection photo 1, 4 September 2023
  • Lamaa construction site, inspection photo 2, 4 September 2023
  • Lamaa construction site, inspection photo 3, 4 September 2023

All 90 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Lamaa?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lamaa handover date?
Construction of Lamaa is recorded as complete, with a registered completion date of January 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lamaa?
Lamaa was 100% built at the site inspection on 14 July 2026. The site has been inspected 11 times since October 2022. The Land Department took 90 site photos at its inspections.
Is Lamaa delayed?
The register lists construction as complete.
Who is building Lamaa?
The registered developer is Jumeirah Hills Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Lamaa?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.