Jumeirah Living Marsa Al Arab construction progress

The register lists Jumeirah Living Marsa Al Arab in Um Suqaim Third as complete, with a registered completion date of November 2022. Its last site inspection on record was in January 2025. The developer is Marsa Al Arab Residences.

100%

Built, at the site inspection of 28 January 2025

Construction complete

Registered completion date
November 2022
Construction started
January 2019
First registered
November 2021
Developer
Marsa Al Arab Residences
Units
31
Escrow bank
Emirates Islamic Bank
Name in Arabic
Jumeirah Living Marsa Al Arab
Project number
1016
Site inspections
3

Schedule

The register lists Jumeirah Living Marsa Al Arab as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 January 2025

100%+12 pts

  • Jumeirah Living Marsa Al Arab construction site, inspection photo 1, 28 January 2025
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 2, 28 January 2025
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 3, 28 January 2025
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 4, 28 January 2025

3 June 2024

88%+8.1 pts

  • Jumeirah Living Marsa Al Arab construction site, inspection photo 1, 3 June 2024
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 2, 3 June 2024
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 3, 3 June 2024
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 4, 3 June 2024

17 April 2023

80%

  • Jumeirah Living Marsa Al Arab construction site, inspection photo 1, 17 April 2023
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 2, 17 April 2023
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 3, 17 April 2023
  • Jumeirah Living Marsa Al Arab construction site, inspection photo 4, 17 April 2023

All 35 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Own a unit in Jumeirah Living Marsa Al Arab?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Jumeirah Living Marsa Al Arab handover date?
Construction of Jumeirah Living Marsa Al Arab is recorded as complete, with a registered completion date of November 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Jumeirah Living Marsa Al Arab?
Jumeirah Living Marsa Al Arab was 100% built at the site inspection on 28 January 2025. The site has been inspected 3 times since April 2023. The Land Department took 35 site photos at its inspections.
Is Jumeirah Living Marsa Al Arab delayed?
The register lists construction as complete.
Who is building Jumeirah Living Marsa Al Arab?
The registered developer is Marsa Al Arab Residences.
Which bank holds the escrow account for Jumeirah Living Marsa Al Arab?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.