54 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Elara was built on the day of each visit.

20 July 202664% built

30 April 202654% built

30 January 202640% built

22 October 202522% built

31 July 20258.4% built

7 May 20250.6% built

25 February 20250% built

23 September 20240% built

5 September 20230% built

Back to Elara construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.