Asayel At Madinat Jumeirah Living construction progress

The register lists Asayel At Madinat Jumeirah Living in Um Suqaim Third as complete, with a registered completion date of May 2023. Its last site inspection on record was in August 2023. The developer is Jumeirah Hills Development.

100%

Built, at the site inspection of 14 August 2023

Construction complete

Registered completion date
May 2023
Construction started
June 2019
First registered
April 2019
Units
307
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أصايل - مدينة جميرا ليفينج
Project number
2146
Site inspections
6

Schedule

The register lists Asayel At Madinat Jumeirah Living as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 August 2023

100%+10.0 pts

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 14 August 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 14 August 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 14 August 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 14 August 2023

21 March 2023

90%+19 pts

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 21 March 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 21 March 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 21 March 2023
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 21 March 2023

20 December 2022

71%+25 pts

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 20 December 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 20 December 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 20 December 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 20 December 2022

31 August 2022

47%+29 pts

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 31 August 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 31 August 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 31 August 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 31 August 2022

24 February 2022

18%+16 pts

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 24 February 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 24 February 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 24 February 2022
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 24 February 2022

12 October 2021

2.0%

  • Asayel At Madinat Jumeirah Living construction site, inspection photo 1, 12 October 2021
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 2, 12 October 2021
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 3, 12 October 2021
  • Asayel At Madinat Jumeirah Living construction site, inspection photo 4, 12 October 2021

All 68 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Asayel At Madinat Jumeirah Living?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Asayel At Madinat Jumeirah Living handover date?
Construction of Asayel At Madinat Jumeirah Living is recorded as complete, with a registered completion date of May 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Asayel At Madinat Jumeirah Living?
Asayel At Madinat Jumeirah Living was 100% built at the site inspection on 14 August 2023. The site has been inspected 6 times since October 2021. The Land Department took 68 site photos at its inspections.
Is Asayel At Madinat Jumeirah Living delayed?
The register lists construction as complete.
Who is building Asayel At Madinat Jumeirah Living?
The registered developer is Jumeirah Hills Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Asayel At Madinat Jumeirah Living?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.