Al Jazi - Madinat Jumeriah Living construction progress

The register lists Al Jazi - Madinat Jumeriah Living in Um Suqaim Third as complete, with a registered completion date of December 2024. Its last site inspection on record was in October 2025. The developer is Jumeirah Hills Development.

100%

Built, at the site inspection of 24 October 2025

Construction complete

Registered completion date
December 2024
Construction started
August 2022
First registered
June 2022
Units
378
Escrow bank
First Abu Dhabi Bank
Name in Arabic
الجازي - مدينة جميرا ليفينج
Project number
2407
Site inspections
7

Schedule

The register lists Al Jazi - Madinat Jumeriah Living as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 October 2025

100%+9.4 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 24 October 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 24 October 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 24 October 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 24 October 2025

20 August 2025

91%+17 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 20 August 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 20 August 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 20 August 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 20 August 2025

29 April 2025

73%+19 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 29 April 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 29 April 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 29 April 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 29 April 2025

15 January 2025

54%+17 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 15 January 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 15 January 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 15 January 2025
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 15 January 2025

23 September 2024

38%+25 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 23 September 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 23 September 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 23 September 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 23 September 2024

4 March 2024

13%+13 pts

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 4 March 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 4 March 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 4 March 2024
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 4 March 2024

4 September 2023

0.3%

  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 1, 4 September 2023
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 2, 4 September 2023
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 3, 4 September 2023
  • Al Jazi - Madinat Jumeriah Living construction site, inspection photo 4, 4 September 2023

All 64 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Al Jazi - Madinat Jumeriah Living?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Al Jazi - Madinat Jumeriah Living handover date?
Construction of Al Jazi - Madinat Jumeriah Living is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Al Jazi - Madinat Jumeriah Living?
Al Jazi - Madinat Jumeriah Living was 100% built at the site inspection on 24 October 2025. The site has been inspected 7 times since September 2023. The Land Department took 64 site photos at its inspections.
Is Al Jazi - Madinat Jumeriah Living delayed?
The register lists construction as complete.
Who is building Al Jazi - Madinat Jumeriah Living?
The registered developer is Jumeirah Hills Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Al Jazi - Madinat Jumeriah Living?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.