Una construction progress

The register lists Una in Town Square as complete, with a registered completion date of March 2021. Its last site inspection on record was in April 2021. The developer is Nshama Properties.

100%

Built, at the site inspection of 1 April 2021

Construction complete

Registered completion date
March 2021
Construction started
January 2018
First registered
October 2017
Community
Town Square
Units
480
Escrow bank
Dubai Islamic Bank
Name in Arabic
انا
Project number
1979
Site inspections
7

Schedule

The register lists Una as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 April 2021

100%+37 pts

  • Una construction site, inspection photo 1, 1 April 2021
  • Una construction site, inspection photo 2, 1 April 2021
  • Una construction site, inspection photo 3, 1 April 2021
  • Una construction site, inspection photo 4, 1 April 2021

11 May 2020

63%+7.8 pts

  • Una construction site, inspection photo 1, 11 May 2020
  • Una construction site, inspection photo 2, 11 May 2020
  • Una construction site, inspection photo 3, 11 May 2020
  • Una construction site, inspection photo 4, 11 May 2020

30 December 2019

56%+26 pts

  • Una construction site, inspection photo 1, 30 December 2019
  • Una construction site, inspection photo 2, 30 December 2019
  • Una construction site, inspection photo 3, 30 December 2019
  • Una construction site, inspection photo 4, 30 December 2019

23 June 2019

30%+8.3 pts

  • Una construction site, inspection photo 1, 23 June 2019
  • Una construction site, inspection photo 2, 23 June 2019
  • Una construction site, inspection photo 3, 23 June 2019
  • Una construction site, inspection photo 4, 23 June 2019

21 February 2019

22%+13 pts

  • Una construction site, inspection photo 1, 21 February 2019
  • Una construction site, inspection photo 2, 21 February 2019
  • Una construction site, inspection photo 3, 21 February 2019
  • Una construction site, inspection photo 4, 21 February 2019

11 November 2018

9.1%+8.7 pts

  • Una construction site, inspection photo 1, 11 November 2018
  • Una construction site, inspection photo 2, 11 November 2018
  • Una construction site, inspection photo 3, 11 November 2018
  • Una construction site, inspection photo 4, 11 November 2018

24 June 2018

0.4%

  • Una construction site, inspection photo 1, 24 June 2018
  • Una construction site, inspection photo 2, 24 June 2018

All 66 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Una?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Una handover date?
Construction of Una is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Una?
Una was 100% built at the site inspection on 1 April 2021. The site has been inspected 7 times since June 2018. The Land Department took 66 site photos at its inspections.
Is Una delayed?
The register lists construction as complete.
Who is building Una?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Una?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.