Una construction progress
The register lists Una in Town Square as complete, with a registered completion date of March 2021. Its last site inspection on record was in April 2021. The developer is Nshama Properties.
100%
Built, at the site inspection of 1 April 2021
Construction complete
- Registered completion date
- March 2021
- Construction started
- January 2018
- First registered
- October 2017
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 480
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- انا
- Project number
- 1979
- Site inspections
- 7
Schedule
The register lists Una as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
1 April 2021
100%+37 pts
11 May 2020
63%+7.8 pts
30 December 2019
56%+26 pts
23 June 2019
30%+8.3 pts
21 February 2019
22%+13 pts
11 November 2018
9.1%+8.7 pts
24 June 2018
0.4%
Context
Town Square has 18 projects under construction, 29% built on average.
Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Una?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Una handover date?
- Construction of Una is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Una?
- Una was 100% built at the site inspection on 1 April 2021. The site has been inspected 7 times since June 2018. The Land Department took 66 site photos at its inspections.
- Is Una delayed?
- The register lists construction as complete.
- Who is building Una?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Una?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SymphonyAlso by Nshama Properties. 73%.
- GroveAlso by Nshama Properties. 41%.
- FiaAlso by Nshama Properties. 85%.
- OraAlso by Nshama Properties. 47%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

