Skip to content

The Diplomat Residences construction progress

The register lists The Diplomat Residences in Town Square as complete, with a registered completion date of November 2024. Its last site inspection on record was in December 2024. The developer is Nshama Properties.

100%

Built, at the site inspection of 12 December 2024

Construction complete

Registered completion date
November 2024
Construction started
March 2023
First registered
February 2023
Community
Town Square
Units
153
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا ديبلومت ريزيدنس
Project number
2524
Site inspections
5

Schedule

The register lists The Diplomat Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 December 2024

100%+38 pts

  • The Diplomat Residences construction site, inspection photo 1, 12 December 2024
  • The Diplomat Residences construction site, inspection photo 2, 12 December 2024
  • The Diplomat Residences construction site, inspection photo 3, 12 December 2024
  • The Diplomat Residences construction site, inspection photo 4, 12 December 2024

10 June 2024

62%+40 pts

  • The Diplomat Residences construction site, inspection photo 1, 10 June 2024
  • The Diplomat Residences construction site, inspection photo 2, 10 June 2024
  • The Diplomat Residences construction site, inspection photo 3, 10 June 2024
  • The Diplomat Residences construction site, inspection photo 4, 10 June 2024

14 December 2023

22%+18 pts

  • The Diplomat Residences construction site, inspection photo 1, 14 December 2023
  • The Diplomat Residences construction site, inspection photo 2, 14 December 2023
  • The Diplomat Residences construction site, inspection photo 3, 14 December 2023
  • The Diplomat Residences construction site, inspection photo 4, 14 December 2023

14 August 2023

4.0%+4.0 pts

  • The Diplomat Residences construction site, inspection photo 1, 14 August 2023
  • The Diplomat Residences construction site, inspection photo 2, 14 August 2023
  • The Diplomat Residences construction site, inspection photo 3, 14 August 2023
  • The Diplomat Residences construction site, inspection photo 4, 14 August 2023

29 November 2022

0%

  • The Diplomat Residences construction site, inspection photo 1, 29 November 2022
  • The Diplomat Residences construction site, inspection photo 2, 29 November 2022

All 27 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Diplomat Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Diplomat Residences handover date?
Construction of The Diplomat Residences is recorded as complete, with a registered completion date of November 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Diplomat Residences?
The Diplomat Residences was 100% built at the site inspection on 12 December 2024. The site has been inspected 5 times since November 2022. The Land Department took 27 site photos at its inspections.
Is The Diplomat Residences delayed?
The register lists construction as complete.
Who is building The Diplomat Residences?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for The Diplomat Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.