The Baltimore construction progress

The Baltimore in Town Square is 8.7% built at the Land Department inspection of March 2026. Developer Nshama Properties. Completion registered for September 2027.

26%

Built, at the Land Department site inspection of 24 March 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
August 2032
Construction started
May 2025
Registered with the Land Department
December 2024
Community
Town Square
Units
167
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا بالتيمور
Land Department project number
3365
Land Department site inspections
3

Schedule

Between November 2025 and March 2026 the site added about 1.2 points a month. At that rate it would finish around August 2032, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 March 2026

8.7%+4.6 pts

  • The Baltimore construction site, Land Department inspection photo 1, 24 March 2026
  • The Baltimore construction site, Land Department inspection photo 2, 24 March 2026
  • The Baltimore construction site, Land Department inspection photo 3, 24 March 2026
  • The Baltimore construction site, Land Department inspection photo 4, 24 March 2026

26 November 2025

4.1%+4.1 pts

  • The Baltimore construction site, Land Department inspection photo 1, 26 November 2025
  • The Baltimore construction site, Land Department inspection photo 2, 26 November 2025
  • The Baltimore construction site, Land Department inspection photo 3, 26 November 2025

30 October 2024

0%

  • The Baltimore construction site, Land Department inspection photo 1, 30 October 2024
  • The Baltimore construction site, Land Department inspection photo 2, 30 October 2024

All 11 site photos, by inspection date

Context

Town Square has 19 projects under construction, 30% built on average.

Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Baltimore?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Baltimore be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around August 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Baltimore is built?
26%, measured at the Land Department site inspection on 24 March 2026. The Land Department engineers have inspected the site 3 times since October 2024.
Is The Baltimore delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building The Baltimore?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for The Baltimore?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.