Savannah construction progress

The registered completion date for Savannah in Town Square is April 2027. At the last site inspection, in September 2026, it was 43% built. The developer is Nshama Properties.

43%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
March 2028
Construction started
December 2024
First registered
July 2024
Community
Town Square
Units
154
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سافانا
Project number
3144
Site inspections
4

Schedule

Between January 2026 and September 2026 the site added about 3.2 points a month. At that rate it would finish around March 2028, more than three months after its registered date of April 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

43%+17 pts

  • Savannah construction site, inspection photo 1, 17 September 2026
  • Savannah construction site, inspection photo 2, 17 September 2026
  • Savannah construction site, inspection photo 3, 17 September 2026
  • Savannah construction site, inspection photo 4, 17 September 2026

30 April 2026

26%+8.9 pts

  • Savannah construction site, inspection photo 1, 30 April 2026
  • Savannah construction site, inspection photo 2, 30 April 2026
  • Savannah construction site, inspection photo 3, 30 April 2026
  • Savannah construction site, inspection photo 4, 30 April 2026

9 January 2026

17%+17 pts

  • Savannah construction site, inspection photo 1, 9 January 2026
  • Savannah construction site, inspection photo 2, 9 January 2026
  • Savannah construction site, inspection photo 3, 9 January 2026

19 June 2024

0%

  • Savannah construction site, inspection photo 1, 19 June 2024
  • Savannah construction site, inspection photo 2, 19 June 2024

All 19 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Savannah?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Savannah handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Savannah?
Savannah was 43% built at the site inspection on 17 September 2026. The site has been inspected 4 times since June 2024. The Land Department took 19 site photos at its inspections.
Is Savannah delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Savannah?
The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Savannah?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.