Savannah construction progress
The registered completion date for Savannah in Town Square is April 2027. At the last site inspection, in September 2026, it was 43% built. The developer is Nshama Properties.
43%
Built, at the site inspection of 17 September 2026
Running behind its date
- Registered completion date
- April 2027
- Finish at recent pace
- March 2028
- Construction started
- December 2024
- First registered
- July 2024
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 154
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سافانا
- Project number
- 3144
- Site inspections
- 4
Schedule
Between January 2026 and September 2026 the site added about 3.2 points a month. At that rate it would finish around March 2028, more than three months after its registered date of April 2027.
Site inspections
17 September 2026
43%+17 pts
30 April 2026
26%+8.9 pts
9 January 2026
17%+17 pts
19 June 2024
0%
Context
Town Square has 18 projects under construction, 29% built on average.
Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Savannah?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Savannah handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Savannah?
- Savannah was 43% built at the site inspection on 17 September 2026. The site has been inspected 4 times since June 2024. The Land Department took 19 site photos at its inspections.
- Is Savannah delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Savannah?
- The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Savannah?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SymphonyAlso by Nshama Properties. 73%.
- GroveAlso by Nshama Properties. 41%.
- FiaAlso by Nshama Properties. 85%.
- OraAlso by Nshama Properties. 47%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.