Safi Townhouses construction progress

The register lists Safi Townhouses in Town Square as complete, with a registered completion date of June 2019. Its last site inspection on record was in June 2019. The developer is Nshmi Development.

100%

Built, at the site inspection of 27 June 2019

Construction complete

Registered completion date
June 2019
Construction started
December 2016
First registered
August 2016
Developer
Nshmi Development
Community
Town Square
Units
315
Escrow bank
Dubai Islamic Bank
Name in Arabic
صافي تاون هاوس
Project number
1787
Site inspections
6

Schedule

The register lists Safi Townhouses as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 June 2019

100%+7.9 pts

  • Safi Townhouses construction site, inspection photo 1, 27 June 2019
  • Safi Townhouses construction site, inspection photo 2, 27 June 2019
  • Safi Townhouses construction site, inspection photo 3, 27 June 2019
  • Safi Townhouses construction site, inspection photo 4, 27 June 2019

24 February 2019

92%+19 pts

  • Safi Townhouses construction site, inspection photo 1, 24 February 2019
  • Safi Townhouses construction site, inspection photo 2, 24 February 2019
  • Safi Townhouses construction site, inspection photo 3, 24 February 2019
  • Safi Townhouses construction site, inspection photo 4, 24 February 2019

17 October 2018

73%+25 pts

  • Safi Townhouses construction site, inspection photo 1, 17 October 2018
  • Safi Townhouses construction site, inspection photo 2, 17 October 2018
  • Safi Townhouses construction site, inspection photo 3, 17 October 2018
  • Safi Townhouses construction site, inspection photo 4, 17 October 2018

24 June 2018

48%+18 pts

  • Safi Townhouses construction site, inspection photo 1, 24 June 2018
  • Safi Townhouses construction site, inspection photo 2, 24 June 2018
  • Safi Townhouses construction site, inspection photo 3, 24 June 2018
  • Safi Townhouses construction site, inspection photo 4, 24 June 2018

19 February 2018

30%+14 pts

  • Safi Townhouses construction site, inspection photo 1, 19 February 2018
  • Safi Townhouses construction site, inspection photo 2, 19 February 2018
  • Safi Townhouses construction site, inspection photo 3, 19 February 2018
  • Safi Townhouses construction site, inspection photo 4, 19 February 2018

8 October 2017

16%

  • Safi Townhouses construction site, inspection photo 1, 8 October 2017
  • Safi Townhouses construction site, inspection photo 2, 8 October 2017
  • Safi Townhouses construction site, inspection photo 3, 8 October 2017

All 47 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Own a unit in Safi Townhouses?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Safi Townhouses handover date?
Construction of Safi Townhouses is recorded as complete, with a registered completion date of June 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Safi Townhouses?
Safi Townhouses was 100% built at the site inspection on 27 June 2019. The site has been inspected 6 times since October 2017. The Land Department took 47 site photos at its inspections.
Is Safi Townhouses delayed?
The register lists construction as complete.
Who is building Safi Townhouses?
The registered developer is Nshmi Development.
Which bank holds the escrow account for Safi Townhouses?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.