Odessa construction progress

The registered completion date for Odessa in Town Square is December 2027. At the last site inspection, in August 2026, it was 8.0% built. The developer is Nshama Properties.

8.0%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
July 2032
Construction started
August 2025
First registered
March 2025
Community
Town Square
Units
178
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أوديسا
Project number
3450
Site inspections
3

Schedule

Between February 2026 and August 2026 the site added about 1.3 points a month. At that rate it would finish around July 2032, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

8.0%+8.0 pts

  • Odessa construction site, inspection photo 1, 13 August 2026
  • Odessa construction site, inspection photo 2, 13 August 2026
  • Odessa construction site, inspection photo 3, 13 August 2026
  • Odessa construction site, inspection photo 4, 13 August 2026

6 February 2026

0%+0.0 pts

  • Odessa construction site, inspection photo 1, 6 February 2026
  • Odessa construction site, inspection photo 2, 6 February 2026
  • Odessa construction site, inspection photo 3, 6 February 2026
  • Odessa construction site, inspection photo 4, 6 February 2026

22 January 2025

0%

  • Odessa construction site, inspection photo 1, 22 January 2025
  • Odessa construction site, inspection photo 2, 22 January 2025

All 10 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Odessa?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Odessa handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Odessa?
Odessa was 8.0% built at the site inspection on 13 August 2026. The site has been inspected 3 times since January 2025. The Land Department took 10 site photos at its inspections.
Is Odessa delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Odessa?
The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Odessa?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.