Maha Townhouses construction progress

The register lists Maha Townhouses in Town Square as complete, with a registered completion date of August 2025. Its last site inspection on record was in May 2025. The developer is Nshama Properties.

100%

Built, at the site inspection of 9 May 2025

Construction complete

Registered completion date
August 2025
Construction started
March 2023
First registered
November 2022
Community
Town Square
Units
501
Escrow bank
First Abu Dhabi Bank
Name in Arabic
مها تاون هاوس
Project number
2490
Site inspections
10

Schedule

The register lists Maha Townhouses as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 May 2025

100%

  • Maha Townhouses construction site, inspection photo 1, 9 May 2025
  • Maha Townhouses construction site, inspection photo 2, 9 May 2025
  • Maha Townhouses construction site, inspection photo 3, 9 May 2025
  • Maha Townhouses construction site, inspection photo 4, 9 May 2025

5 May 2025

100%+13 pts

  • Maha Townhouses construction site, inspection photo 1, 5 May 2025
  • Maha Townhouses construction site, inspection photo 2, 5 May 2025
  • Maha Townhouses construction site, inspection photo 3, 5 May 2025
  • Maha Townhouses construction site, inspection photo 4, 5 May 2025

8 January 2025

87%+7.0 pts

  • Maha Townhouses construction site, inspection photo 1, 8 January 2025
  • Maha Townhouses construction site, inspection photo 2, 8 January 2025
  • Maha Townhouses construction site, inspection photo 3, 8 January 2025
  • Maha Townhouses construction site, inspection photo 4, 8 January 2025

29 October 2024

80%+20 pts

  • Maha Townhouses construction site, inspection photo 1, 29 October 2024
  • Maha Townhouses construction site, inspection photo 2, 29 October 2024
  • Maha Townhouses construction site, inspection photo 3, 29 October 2024
  • Maha Townhouses construction site, inspection photo 4, 29 October 2024

1 July 2024

60%+5.3 pts

  • Maha Townhouses construction site, inspection photo 1, 1 July 2024
  • Maha Townhouses construction site, inspection photo 2, 1 July 2024
  • Maha Townhouses construction site, inspection photo 3, 1 July 2024
  • Maha Townhouses construction site, inspection photo 4, 1 July 2024

10 June 2024

55%+20 pts

  • Maha Townhouses construction site, inspection photo 1, 10 June 2024
  • Maha Townhouses construction site, inspection photo 2, 10 June 2024
  • Maha Townhouses construction site, inspection photo 3, 10 June 2024
  • Maha Townhouses construction site, inspection photo 4, 10 June 2024

26 March 2024

35%+28 pts

  • Maha Townhouses construction site, inspection photo 1, 26 March 2024
  • Maha Townhouses construction site, inspection photo 2, 26 March 2024
  • Maha Townhouses construction site, inspection photo 3, 26 March 2024
  • Maha Townhouses construction site, inspection photo 4, 26 March 2024

5 October 2023

7.0%+6.7 pts

  • Maha Townhouses construction site, inspection photo 1, 5 October 2023
  • Maha Townhouses construction site, inspection photo 2, 5 October 2023
  • Maha Townhouses construction site, inspection photo 3, 5 October 2023
  • Maha Townhouses construction site, inspection photo 4, 5 October 2023

25 April 2023

0.3%+0.3 pts

  • Maha Townhouses construction site, inspection photo 1, 25 April 2023
  • Maha Townhouses construction site, inspection photo 2, 25 April 2023
  • Maha Townhouses construction site, inspection photo 3, 25 April 2023
  • Maha Townhouses construction site, inspection photo 4, 25 April 2023

18 October 2022

0%

  • Maha Townhouses construction site, inspection photo 1, 18 October 2022
  • Maha Townhouses construction site, inspection photo 2, 18 October 2022
  • Maha Townhouses construction site, inspection photo 3, 18 October 2022
  • Maha Townhouses construction site, inspection photo 4, 18 October 2022

All 67 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Maha Townhouses?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Maha Townhouses handover date?
Construction of Maha Townhouses is recorded as complete, with a registered completion date of August 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Maha Townhouses?
Maha Townhouses was 100% built at the site inspection on 9 May 2025. The site has been inspected 10 times since October 2022. The Land Department took 67 site photos at its inspections.
Is Maha Townhouses delayed?
The register lists construction as complete.
Who is building Maha Townhouses?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Maha Townhouses?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.