Liva construction progress

The register lists Liva in Town Square as complete, with a registered completion date of September 2025. Its last site inspection on record was in February 2025. The developer is Nshama Properties.

100%

Built, at the site inspection of 3 February 2025

Construction complete

Registered completion date
September 2025
Construction started
February 2023
First registered
October 2022
Community
Town Square
Units
484
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ليفا
Project number
2492
Site inspections
7

Schedule

The register lists Liva as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 February 2025

100%+13 pts

  • Liva construction site, inspection photo 1, 3 February 2025
  • Liva construction site, inspection photo 2, 3 February 2025
  • Liva construction site, inspection photo 3, 3 February 2025
  • Liva construction site, inspection photo 4, 3 February 2025

4 September 2024

87%+13 pts

  • Liva construction site, inspection photo 1, 4 September 2024
  • Liva construction site, inspection photo 2, 4 September 2024
  • Liva construction site, inspection photo 3, 4 September 2024
  • Liva construction site, inspection photo 4, 4 September 2024

7 June 2024

74%+16 pts

  • Liva construction site, inspection photo 1, 7 June 2024
  • Liva construction site, inspection photo 2, 7 June 2024
  • Liva construction site, inspection photo 3, 7 June 2024
  • Liva construction site, inspection photo 4, 7 June 2024

11 March 2024

58%+13 pts

  • Liva construction site, inspection photo 1, 11 March 2024
  • Liva construction site, inspection photo 2, 11 March 2024
  • Liva construction site, inspection photo 3, 11 March 2024
  • Liva construction site, inspection photo 4, 11 March 2024

6 October 2023

46%+23 pts

  • Liva construction site, inspection photo 1, 6 October 2023
  • Liva construction site, inspection photo 2, 6 October 2023
  • Liva construction site, inspection photo 3, 6 October 2023
  • Liva construction site, inspection photo 4, 6 October 2023

25 April 2023

22%+21 pts

  • Liva construction site, inspection photo 1, 25 April 2023
  • Liva construction site, inspection photo 2, 25 April 2023
  • Liva construction site, inspection photo 3, 25 April 2023
  • Liva construction site, inspection photo 4, 25 April 2023

18 October 2022

1.0%

  • Liva construction site, inspection photo 1, 18 October 2022
  • Liva construction site, inspection photo 2, 18 October 2022
  • Liva construction site, inspection photo 3, 18 October 2022
  • Liva construction site, inspection photo 4, 18 October 2022

All 54 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Liva?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Liva handover date?
Construction of Liva is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Liva?
Liva was 100% built at the site inspection on 3 February 2025. The site has been inspected 7 times since October 2022. The Land Department took 54 site photos at its inspections.
Is Liva delayed?
The register lists construction as complete.
Who is building Liva?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Liva?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.