Holland Gardens construction progress

The register lists Holland Gardens in Town Square as complete, with a registered completion date of September 2025. Its last site inspection on record was in November 2025. The developer is Nshama Properties.

100%

Built, at the site inspection of 11 November 2025

Construction complete

Registered completion date
September 2025
Construction started
September 2024
First registered
May 2023
Community
Town Square
Units
228
Escrow bank
First Abu Dhabi Bank
Name in Arabic
هولاند جاردنس
Project number
2526
Site inspections
9

Schedule

The register lists Holland Gardens as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 November 2025

100%+21 pts

  • Holland Gardens construction site, inspection photo 1, 11 November 2025
  • Holland Gardens construction site, inspection photo 2, 11 November 2025
  • Holland Gardens construction site, inspection photo 3, 11 November 2025
  • Holland Gardens construction site, inspection photo 4, 11 November 2025

3 July 2025

79%+23 pts

  • Holland Gardens construction site, inspection photo 1, 3 July 2025
  • Holland Gardens construction site, inspection photo 2, 3 July 2025
  • Holland Gardens construction site, inspection photo 3, 3 July 2025
  • Holland Gardens construction site, inspection photo 4, 3 July 2025

13 March 2025

56%+9.8 pts

  • Holland Gardens construction site, inspection photo 1, 13 March 2025
  • Holland Gardens construction site, inspection photo 2, 13 March 2025
  • Holland Gardens construction site, inspection photo 3, 13 March 2025
  • Holland Gardens construction site, inspection photo 4, 13 March 2025

14 January 2025

46%+14 pts

  • Holland Gardens construction site, inspection photo 1, 14 January 2025
  • Holland Gardens construction site, inspection photo 2, 14 January 2025
  • Holland Gardens construction site, inspection photo 3, 14 January 2025
  • Holland Gardens construction site, inspection photo 4, 14 January 2025

4 September 2024

32%+22 pts

  • Holland Gardens construction site, inspection photo 1, 4 September 2024
  • Holland Gardens construction site, inspection photo 2, 4 September 2024
  • Holland Gardens construction site, inspection photo 3, 4 September 2024
  • Holland Gardens construction site, inspection photo 4, 4 September 2024

7 June 2024

11%+6.5 pts

  • Holland Gardens construction site, inspection photo 1, 7 June 2024
  • Holland Gardens construction site, inspection photo 2, 7 June 2024
  • Holland Gardens construction site, inspection photo 3, 7 June 2024
  • Holland Gardens construction site, inspection photo 4, 7 June 2024

26 March 2024

4.1%+4.1 pts

  • Holland Gardens construction site, inspection photo 1, 26 March 2024
  • Holland Gardens construction site, inspection photo 2, 26 March 2024
  • Holland Gardens construction site, inspection photo 3, 26 March 2024
  • Holland Gardens construction site, inspection photo 4, 26 March 2024

14 August 2023

0%

  • Holland Gardens construction site, inspection photo 1, 14 August 2023
  • Holland Gardens construction site, inspection photo 2, 14 August 2023

29 November 2022

0%

  • Holland Gardens construction site, inspection photo 1, 29 November 2022
  • Holland Gardens construction site, inspection photo 2, 29 November 2022

All 56 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Holland Gardens?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Holland Gardens handover date?
Construction of Holland Gardens is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Holland Gardens?
Holland Gardens was 100% built at the site inspection on 11 November 2025. The site has been inspected 9 times since November 2022. The Land Department took 56 site photos at its inspections.
Is Holland Gardens delayed?
The register lists construction as complete.
Who is building Holland Gardens?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Holland Gardens?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.