Hillcrest construction progress
The registered completion date for Hillcrest in Town Square is June 2027. At the last site inspection, in September 2026, it was 38% built. The developer is Nshama Properties.
38%
Built, at the site inspection of 17 September 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- April 2028
- Construction started
- March 2025
- First registered
- September 2024
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 171
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- هيلكريست
- Project number
- 3211
- Site inspections
- 4
Schedule
Between January 2026 and September 2026 the site added about 3.3 points a month. At that rate it would finish around April 2028, more than three months after its registered date of June 2027.
Site inspections
17 September 2026
38%+20 pts
30 April 2026
18%+7.3 pts
9 January 2026
11%+11 pts
6 August 2024
0%
Context
Town Square has 18 projects under construction, 29% built on average.
Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Hillcrest?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Hillcrest handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Hillcrest?
- Hillcrest was 38% built at the site inspection on 17 September 2026. The site has been inspected 4 times since August 2024. The Land Department took 21 site photos at its inspections.
- Is Hillcrest delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Hillcrest?
- The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Hillcrest?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SymphonyAlso by Nshama Properties. 73%.
- GroveAlso by Nshama Properties. 41%.
- FiaAlso by Nshama Properties. 85%.
- OraAlso by Nshama Properties. 47%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.