Hayat Boulevard construction progress

The register lists Hayat Boulevard in Town Square as complete, with a registered completion date of February 2020. Its last site inspection on record was in December 2020. The developer is Nshmi Development.

100%

Built, at the site inspection of 30 December 2020

Construction complete

Registered completion date
February 2020
Construction started
October 2016
First registered
May 2016
Developer
Nshmi Development
Community
Town Square
Units
678
Escrow bank
Dubai Islamic Bank
Name in Arabic
Hayat Boulevard
Project number
1755
Site inspections
10

Schedule

The register lists Hayat Boulevard as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 December 2020

97%

  • Hayat Boulevard construction site, inspection photo 1, 30 December 2020
  • Hayat Boulevard construction site, inspection photo 2, 30 December 2020
  • Hayat Boulevard construction site, inspection photo 3, 30 December 2020
  • Hayat Boulevard construction site, inspection photo 4, 30 December 2020

4 February 2020

100%+6.9 pts

  • Hayat Boulevard construction site, inspection photo 1, 4 February 2020
  • Hayat Boulevard construction site, inspection photo 2, 4 February 2020
  • Hayat Boulevard construction site, inspection photo 3, 4 February 2020
  • Hayat Boulevard construction site, inspection photo 4, 4 February 2020

24 September 2019

93%+8.1 pts

  • Hayat Boulevard construction site, inspection photo 1, 24 September 2019
  • Hayat Boulevard construction site, inspection photo 2, 24 September 2019
  • Hayat Boulevard construction site, inspection photo 3, 24 September 2019
  • Hayat Boulevard construction site, inspection photo 4, 24 September 2019

29 May 2019

85%+8.8 pts

  • Hayat Boulevard construction site, inspection photo 1, 29 May 2019
  • Hayat Boulevard construction site, inspection photo 2, 29 May 2019
  • Hayat Boulevard construction site, inspection photo 3, 29 May 2019
  • Hayat Boulevard construction site, inspection photo 4, 29 May 2019

21 February 2019

76%+5.5 pts

  • Hayat Boulevard construction site, inspection photo 1, 21 February 2019
  • Hayat Boulevard construction site, inspection photo 2, 21 February 2019
  • Hayat Boulevard construction site, inspection photo 3, 21 February 2019
  • Hayat Boulevard construction site, inspection photo 4, 21 February 2019

11 November 2018

71%+13 pts

  • Hayat Boulevard construction site, inspection photo 1, 11 November 2018
  • Hayat Boulevard construction site, inspection photo 2, 11 November 2018
  • Hayat Boulevard construction site, inspection photo 3, 11 November 2018
  • Hayat Boulevard construction site, inspection photo 4, 11 November 2018

24 June 2018

58%+13 pts

  • Hayat Boulevard construction site, inspection photo 1, 24 June 2018
  • Hayat Boulevard construction site, inspection photo 2, 24 June 2018
  • Hayat Boulevard construction site, inspection photo 3, 24 June 2018
  • Hayat Boulevard construction site, inspection photo 4, 24 June 2018

19 February 2018

45%+15 pts

  • Hayat Boulevard construction site, inspection photo 1, 19 February 2018
  • Hayat Boulevard construction site, inspection photo 2, 19 February 2018
  • Hayat Boulevard construction site, inspection photo 3, 19 February 2018

8 October 2017

31%+31 pts

  • Hayat Boulevard construction site, inspection photo 1, 8 October 2017
  • Hayat Boulevard construction site, inspection photo 2, 8 October 2017

11 January 2017

0%

  • Hayat Boulevard construction site, inspection photo 1, 11 January 2017
  • Hayat Boulevard construction site, inspection photo 2, 11 January 2017

All 80 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Own a unit in Hayat Boulevard?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hayat Boulevard handover date?
Construction of Hayat Boulevard is recorded as complete, with a registered completion date of February 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hayat Boulevard?
Hayat Boulevard was 100% built at the site inspection on 30 December 2020. The site has been inspected 10 times since January 2017. The Land Department took 80 site photos at its inspections.
Is Hayat Boulevard delayed?
The register lists construction as complete.
Who is building Hayat Boulevard?
The registered developer is Nshmi Development.
Which bank holds the escrow account for Hayat Boulevard?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.