Haya On The Park construction progress
Haya On The Park in Town Square is 35% built at the Land Department inspection of September 2026. Developer Nshama Properties. Completion registered for February 2027.
35%
Built, at the Land Department site inspection of 10 September 2026
Running behind its date
- Completion date (Land Department)
- February 2027
- Finish at recent pace
- November 2028
- Construction started
- November 2024
- Registered with the Land Department
- July 2024
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 196
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- هيا أون ذا بارك
- Land Department project number
- 3050
- Land Department site inspections
- 5
Schedule
Between November 2025 and September 2026 the site added about 2.5 points a month. At that rate it would finish around November 2028, more than three months after the February 2027 date registered with the Land Department.
Site inspections
10 September 2026
35%+12 pts
25 March 2026
23%+12 pts
13 November 2025
11%+5.6 pts
7 July 2025
5.3%+5.3 pts
22 April 2024
0%
Context
Town Square has 19 projects under construction, 30% built on average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Haya On The Park?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Haya On The Park be completed?
- The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around November 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Haya On The Park is built?
- 35%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 5 times since April 2024.
- Is Haya On The Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Haya On The Park?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Haya On The Park?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

