Ellison construction progress

Ellison in Town Square is 40% built at the Land Department inspection of September 2026. Developer Nshama Properties. Completion registered for November 2027.

40%

Built, at the Land Department site inspection of 17 September 2026

On pace for its date

Completion date (Land Department)
November 2027
Finish at recent pace
November 2027
Construction started
July 2025
Registered with the Land Department
January 2025
Community
Town Square
Units
148
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إليسون
Land Department project number
3451
Land Department site inspections
4

Schedule

Since January 2026 Ellison has added about 4.3 points a month. That puts 100% around November 2027, within three months of its registered completion date of November 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 September 2026

40%+25 pts

  • Ellison construction site, Land Department inspection photo 1, 17 September 2026
  • Ellison construction site, Land Department inspection photo 2, 17 September 2026
  • Ellison construction site, Land Department inspection photo 3, 17 September 2026
  • Ellison construction site, Land Department inspection photo 4, 17 September 2026

30 April 2026

15%+10 pts

  • Ellison construction site, Land Department inspection photo 1, 30 April 2026
  • Ellison construction site, Land Department inspection photo 2, 30 April 2026
  • Ellison construction site, Land Department inspection photo 3, 30 April 2026
  • Ellison construction site, Land Department inspection photo 4, 30 April 2026

9 January 2026

5.0%+5.0 pts

  • Ellison construction site, Land Department inspection photo 1, 9 January 2026
  • Ellison construction site, Land Department inspection photo 2, 9 January 2026
  • Ellison construction site, Land Department inspection photo 3, 9 January 2026

22 January 2025

0%

  • Ellison construction site, Land Department inspection photo 1, 22 January 2025
  • Ellison construction site, Land Department inspection photo 2, 22 January 2025
  • Ellison construction site, Land Department inspection photo 3, 22 January 2025

All 21 site photos, by inspection date

Context

Town Square has 19 projects under construction, 30% built on average. Ellison is ahead of that average.

Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ellison?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Ellison be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ellison is built?
40%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 4 times since January 2025.
Is Ellison delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
Who is building Ellison?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Ellison?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.