Ellison construction progress
Ellison in Town Square is 40% built at the Land Department inspection of September 2026. Developer Nshama Properties. Completion registered for November 2027.
40%
Built, at the Land Department site inspection of 17 September 2026
On pace for its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- November 2027
- Construction started
- July 2025
- Registered with the Land Department
- January 2025
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 148
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- إليسون
- Land Department project number
- 3451
- Land Department site inspections
- 4
Schedule
Since January 2026 Ellison has added about 4.3 points a month. That puts 100% around November 2027, within three months of its registered completion date of November 2027.
Site inspections
17 September 2026
40%+25 pts
30 April 2026
15%+10 pts
9 January 2026
5.0%+5.0 pts
22 January 2025
0%
Context
Town Square has 19 projects under construction, 30% built on average. Ellison is ahead of that average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ellison?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Ellison be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ellison is built?
- 40%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 4 times since January 2025.
- Is Ellison delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
- Who is building Ellison?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Ellison?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.