Ellison construction progress

The registered completion date for Ellison in Town Square is November 2027. At the last site inspection, in September 2026, it was 40% built. The developer is Nshama Properties.

40%

Built, at the site inspection of 17 September 2026

On pace for its date

Registered completion date
November 2027
Finish at recent pace
November 2027
Construction started
July 2025
First registered
January 2025
Community
Town Square
Units
148
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إليسون
Project number
3451
Site inspections
4

Schedule

Since January 2026 Ellison has added about 4.3 points a month. That puts 100% around November 2027, within three months of its registered completion date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

40%+25 pts

  • Ellison construction site, inspection photo 1, 17 September 2026
  • Ellison construction site, inspection photo 2, 17 September 2026
  • Ellison construction site, inspection photo 3, 17 September 2026
  • Ellison construction site, inspection photo 4, 17 September 2026

30 April 2026

15%+10 pts

  • Ellison construction site, inspection photo 1, 30 April 2026
  • Ellison construction site, inspection photo 2, 30 April 2026
  • Ellison construction site, inspection photo 3, 30 April 2026
  • Ellison construction site, inspection photo 4, 30 April 2026

9 January 2026

5.0%+5.0 pts

  • Ellison construction site, inspection photo 1, 9 January 2026
  • Ellison construction site, inspection photo 2, 9 January 2026
  • Ellison construction site, inspection photo 3, 9 January 2026

22 January 2025

0%

  • Ellison construction site, inspection photo 1, 22 January 2025
  • Ellison construction site, inspection photo 2, 22 January 2025
  • Ellison construction site, inspection photo 3, 22 January 2025

All 21 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ellison?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ellison handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ellison?
Ellison was 40% built at the site inspection on 17 September 2026. The site has been inspected 4 times since January 2025. The Land Department took 21 site photos at its inspections.
Is Ellison delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
Who is building Ellison?
The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Ellison?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.