Berkshire Park construction progress
Berkshire Park in Town Square is 5.2% built at the Land Department inspection of March 2026. Developer Nshama Properties. Completion registered for June 2027.
18%
Built, at the Land Department site inspection of 23 March 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- April 2035
- Construction started
- March 2025
- Registered with the Land Department
- October 2024
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 149
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بيركشاير بارك
- Land Department project number
- 3312
- Land Department site inspections
- 3
Schedule
Between November 2025 and March 2026 the site added about 0.9 points a month. At that rate it would finish around April 2035, more than three months after the June 2027 date registered with the Land Department.
Site inspections
23 March 2026
5.2%+3.4 pts
26 November 2025
1.8%+1.8 pts
1 October 2024
0%
Context
Town Square has 19 projects under construction, 30% built on average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Berkshire Park?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Berkshire Park be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around April 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Berkshire Park is built?
- 18%, measured at the Land Department site inspection on 23 March 2026. The Land Department engineers have inspected the site 3 times since October 2024.
- Is Berkshire Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Berkshire Park?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Berkshire Park?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)