Alton construction progress

The registered completion date for Alton in Town Square is May 2028. At the last site inspection, in August 2026, it was 5.2% built. The developer is Nshama Properties.

5.2%

Built, at the site inspection of 18 August 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
December 2035
Construction started
November 2025
First registered
May 2025
Community
Town Square
Units
149
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ألتون
Project number
3685
Site inspections
3

Schedule

Between February 2026 and August 2026 the site added about 0.8 points a month. At that rate it would finish around December 2035, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 August 2026

5.2%+5.1 pts

  • Alton construction site, inspection photo 1, 18 August 2026
  • Alton construction site, inspection photo 2, 18 August 2026
  • Alton construction site, inspection photo 3, 18 August 2026
  • Alton construction site, inspection photo 4, 18 August 2026

16 February 2026

0%+0.0 pts

  • Alton construction site, inspection photo 1, 16 February 2026
  • Alton construction site, inspection photo 2, 16 February 2026

22 April 2025

0%

  • Alton construction site, inspection photo 1, 22 April 2025
  • Alton construction site, inspection photo 2, 22 April 2025

All 8 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Alton?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Alton handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Alton?
Alton was 5.2% built at the site inspection on 18 August 2026. The site has been inspected 3 times since April 2025. The Land Department took 8 site photos at its inspections.
Is Alton delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Alton?
The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Alton?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.