Sobha Creek Vistas Heights construction progress
Sobha Creek Vistas Heights in Sobha Hartland is 92% built at the Land Department inspection of September 2026. Developer Sobha.
92%
Built, at the Land Department site inspection of 8 September 2026
- Finish at recent pace
- November 2026
- Construction started
- March 2023
- Registered with the Land Department
- July 2023
- Developer
- Sobha
- Community
- Sobha Hartland
- Units
- 1,354
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- شوبا كريك فيستا هايتس
- Land Department project number
- 2717
- Land Department site inspections
- 10
Schedule
Since November 2025 Sobha Creek Vistas Heights has added about 3.1 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.
Site inspections
8 September 2026
92%+9.2 pts
8 June 2026
82%+7.5 pts
5 March 2026
75%+15 pts
5 November 2025
60%+17 pts
19 May 2025
43%+8.6 pts
7 February 2025
34%+9.0 pts
17 October 2024
25%+4.9 pts
23 May 2024
20%+9.1 pts
30 November 2023
11%+5.1 pts
7 July 2023
5.9%
Context
Sobha Hartland has 3 projects under construction, 82% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Creek Vistas Heights?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Sobha Creek Vistas Heights be completed?
- The Land Department has no completion date on record for Sobha Creek Vistas Heights yet.
- How much of Sobha Creek Vistas Heights is built?
- 92%, measured at the Land Department site inspection on 8 September 2026. The Land Department engineers have inspected the site 10 times since July 2023.
- Who is building Sobha Creek Vistas Heights?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Creek Vistas Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- 330 Riverside CrescentAlso by Sobha. 60%.
- The HighburyNearby in Sobha Hartland. 80%.
- Casa SereneNearby in Sobha Hartland. 74%, Due December 2024, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)