41 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Damac Casa was built on the day of each visit.

18 August 202634% built

21 April 202626% built

22 December 202519% built

20 August 202512% built

10 April 20257.3% built

27 December 20243.9% built

20 May 20240.1% built

28 September 20230% built

Back to Damac Casa construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.