Damac Casa construction photos
41 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Damac Casa was built on the day of each visit.
18 August 202634% built
21 April 202626% built
22 December 202519% built
20 August 202512% built
10 April 20257.3% built
27 December 20243.9% built
20 May 20240.1% built
28 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.