The Palm Crown construction progress
The Palm Crown in Palm Jumeirah is 11% built at the Land Department inspection of July 2026. Developer The Pointe. Completion registered for July 2027.
11%
Built, at the Land Department site inspection of 21 July 2026
Running behind its date
- Completion date (Land Department)
- July 2027
- Finish at recent pace
- June 2046
- Construction started
- July 2024
- Registered with the Land Department
- February 2024
- Developer
- The Pointe
- Community
- Palm Jumeirah
- Units
- 38
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا بالم كراون
- Land Department project number
- 2954
- Land Department site inspections
- 2
Schedule
Between February 2024 and July 2026 the site added about 0.4 points a month. At that rate it would finish around June 2046, more than three months after the July 2027 date registered with the Land Department.
Site inspections
21 July 2026
11%+11 pts
2 February 2024
0%
Context
Palm Jumeirah has 18 projects under construction, 48% built on average.
Own a unit in The Palm Crown?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Palm Crown be completed?
- The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around June 2046. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Palm Crown is built?
- 11%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 2 times since February 2024.
- Is The Palm Crown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building The Palm Crown?
- The registered developer is The Pointe.
- Which bank holds the escrow account for The Palm Crown?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ava At Palm Jumeirah By OmniyatNearby in Palm Jumeirah. 96%, Due June 2026, passed.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.