The Palm Crown construction progress
The registered completion date for The Palm Crown in Palm Jumeirah is July 2027. At the last site inspection, in November 2026, it was 22% built. The developer is The Pointe.
22%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- July 2027
- Finish at recent pace
- January 2029
- Construction started
- July 2024
- First registered
- February 2024
- Developer
- The Pointe
- Community
- Palm Jumeirah
- Units
- 38
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا بالم كراون
- Project number
- 2954
- Site inspections
- 3
Schedule
Between July 2026 and November 2026 the site added about 3.0 points a month. At that rate it would finish around January 2029, more than three months after its registered date of July 2027.
Site inspections
9 November 2026
22%+11 pts
21 July 2026
11%+11 pts
2 February 2024
0%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Own a unit in The Palm Crown?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Palm Crown handover date?
- The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Palm Crown?
- The Palm Crown was 22% built at the site inspection on 9 November 2026. The site has been inspected 3 times since February 2024. The Land Department took 22 site photos at its inspections.
- Is The Palm Crown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building The Palm Crown?
- The registered developer is The Pointe.
- Which bank holds the escrow account for The Palm Crown?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)