The Palm Crown construction progress

The Palm Crown in Palm Jumeirah is 11% built at the Land Department inspection of July 2026. Developer The Pointe. Completion registered for July 2027.

11%

Built, at the Land Department site inspection of 21 July 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
June 2046
Construction started
July 2024
Registered with the Land Department
February 2024
Developer
The Pointe
Community
Palm Jumeirah
Units
38
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا بالم كراون
Land Department project number
2954
Land Department site inspections
2

Schedule

Between February 2024 and July 2026 the site added about 0.4 points a month. At that rate it would finish around June 2046, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

11%+11 pts

  • The Palm Crown construction site, Land Department inspection photo 1, 21 July 2026
  • The Palm Crown construction site, Land Department inspection photo 2, 21 July 2026
  • The Palm Crown construction site, Land Department inspection photo 3, 21 July 2026
  • The Palm Crown construction site, Land Department inspection photo 4, 21 July 2026

2 February 2024

0%

  • The Palm Crown construction site, Land Department inspection photo 1, 2 February 2024
  • The Palm Crown construction site, Land Department inspection photo 2, 2 February 2024

All 9 site photos, by inspection date

Context

Palm Jumeirah has 18 projects under construction, 48% built on average.

Own a unit in The Palm Crown?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Palm Crown be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around June 2046. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Palm Crown is built?
11%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 2 times since February 2024.
Is The Palm Crown delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building The Palm Crown?
The registered developer is The Pointe.
Which bank holds the escrow account for The Palm Crown?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.