The 8 construction progress

The register lists The 8 in Palm Jumeirah as complete, with a registered completion date of August 2019. Its last site inspection on record was in July 2019. The developer is C Fourteen.

100%

Built, at the site inspection of 29 July 2019

Construction complete

Registered completion date
August 2019
Construction started
October 2014
First registered
December 2014
Developer
C Fourteen
Community
Palm Jumeirah
Units
305
Escrow bank
Invest Bank
Name in Arabic
ذا 8
Project number
1617
Site inspections
11

Schedule

The register lists The 8 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 July 2019

100%+11 pts

  • The 8 construction site, inspection photo 1, 29 July 2019
  • The 8 construction site, inspection photo 2, 29 July 2019
  • The 8 construction site, inspection photo 3, 29 July 2019
  • The 8 construction site, inspection photo 4, 29 July 2019

21 March 2019

89%+4.9 pts

  • The 8 construction site, inspection photo 1, 21 March 2019
  • The 8 construction site, inspection photo 2, 21 March 2019
  • The 8 construction site, inspection photo 3, 21 March 2019
  • The 8 construction site, inspection photo 4, 21 March 2019

23 October 2018

84%+7.6 pts

  • The 8 construction site, inspection photo 1, 23 October 2018
  • The 8 construction site, inspection photo 2, 23 October 2018
  • The 8 construction site, inspection photo 3, 23 October 2018
  • The 8 construction site, inspection photo 4, 23 October 2018

18 June 2018

76%+5.5 pts

  • The 8 construction site, inspection photo 1, 18 June 2018
  • The 8 construction site, inspection photo 2, 18 June 2018
  • The 8 construction site, inspection photo 3, 18 June 2018
  • The 8 construction site, inspection photo 4, 18 June 2018

28 January 2018

71%+9.1 pts

  • The 8 construction site, inspection photo 1, 28 January 2018
  • The 8 construction site, inspection photo 2, 28 January 2018
  • The 8 construction site, inspection photo 3, 28 January 2018
  • The 8 construction site, inspection photo 4, 28 January 2018

24 October 2017

62%+11 pts

  • The 8 construction site, inspection photo 1, 24 October 2017
  • The 8 construction site, inspection photo 2, 24 October 2017
  • The 8 construction site, inspection photo 3, 24 October 2017
  • The 8 construction site, inspection photo 4, 24 October 2017

3 July 2017

51%+9.4 pts

  • The 8 construction site, inspection photo 1, 3 July 2017
  • The 8 construction site, inspection photo 2, 3 July 2017
  • The 8 construction site, inspection photo 3, 3 July 2017
  • The 8 construction site, inspection photo 4, 3 July 2017

4 December 2016

41%+10 pts

  • The 8 construction site, inspection photo 1, 4 December 2016
  • The 8 construction site, inspection photo 2, 4 December 2016
  • The 8 construction site, inspection photo 3, 4 December 2016
  • The 8 construction site, inspection photo 4, 4 December 2016

27 April 2016

31%+10 pts

  • The 8 construction site, inspection photo 1, 27 April 2016
  • The 8 construction site, inspection photo 2, 27 April 2016
  • The 8 construction site, inspection photo 3, 27 April 2016
  • The 8 construction site, inspection photo 4, 27 April 2016

5 January 2016

20%+18 pts

  • The 8 construction site, inspection photo 1, 5 January 2016
  • The 8 construction site, inspection photo 2, 5 January 2016
  • The 8 construction site, inspection photo 3, 5 January 2016
  • The 8 construction site, inspection photo 4, 5 January 2016

All 115 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in The 8?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The 8 handover date?
Construction of The 8 is recorded as complete, with a registered completion date of August 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The 8?
The 8 was 100% built at the site inspection on 29 July 2019. The site has been inspected 11 times since February 2015. The Land Department took 115 site photos at its inspections.
Is The 8 delayed?
The register lists construction as complete.
Who is building The 8?
The registered developer is C Fourteen.
Which bank holds the escrow account for The 8?
Invest Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.