Sls Residences At Palm Jumeirah construction progress
Sls Residences At Palm Jumeirah in Palm Jumeirah is 60% built at the Land Department inspection of May 2026. Developer Roya Lifestyle Developments. Completion registered for July 2026.
60%
Built, at the Land Department site inspection of 18 May 2026
2 months past its registered completion date
- Completion date (Land Department)
- July 2026
- Finish at recent pace
- May 2027
- Construction started
- August 2023
- Registered with the Land Department
- July 2023
- Developer
- Roya Lifestyle Developments
- Community
- Palm Jumeirah
- Units
- 114
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- س ل س ريزيدنسز أت بالم جميرا
- Land Department project number
- 2692
- Land Department site inspections
- 9
Schedule
Sls Residences At Palm Jumeirah was registered to complete in July 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around May 2027.
Site inspections
18 May 2026
60%+18 pts
19 February 2026
42%+3.6 pts
4 November 2025
38%+8.7 pts
21 August 2025
29%+11 pts
16 May 2025
19%+5.5 pts
20 February 2025
13%+8.0 pts
12 September 2024
5.1%+3.6 pts
3 June 2024
1.6%+1.6 pts
2 June 2023
0%
Context
Palm Jumeirah has 18 projects under construction, 48% built on average. Sls Residences At Palm Jumeirah is ahead of that average.
Own a unit in Sls Residences At Palm Jumeirah?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sls Residences At Palm Jumeirah be completed?
- The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sls Residences At Palm Jumeirah is built?
- 60%, measured at the Land Department site inspection on 18 May 2026. The Land Department engineers have inspected the site 9 times since June 2023.
- Is Sls Residences At Palm Jumeirah delayed?
- Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
- Who is building Sls Residences At Palm Jumeirah?
- The registered developer is Roya Lifestyle Developments.
- Which bank holds the escrow account for Sls Residences At Palm Jumeirah?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ava At Palm Jumeirah By OmniyatNearby in Palm Jumeirah. 96%, Due June 2026, passed.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)