Olaia Residences construction progress
The registered completion date for Olaia Residences in Palm Jumeirah is December 2027. At the last site inspection, in July 2026, it was 14% built. The developer is Gulf House Real Estate Development.
14%
Built, at the site inspection of 21 July 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- December 2031
- Construction started
- August 2023
- First registered
- April 2025
- Developer
- Gulf House Real Estate Development
- Community
- Palm Jumeirah
- Units
- 149
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أولايا ريزيدنسز
- Project number
- 3519
- Site inspections
- 4
Schedule
Between December 2025 and July 2026 the site added about 1.3 points a month. At that rate it would finish around December 2031, more than three months after its registered date of December 2027.
Site inspections
21 July 2026
14%+4.7 pts
26 March 2026
9.6%+4.9 pts
11 December 2025
4.7%+3.2 pts
18 February 2025
1.5%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Own a unit in Olaia Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Olaia Residences handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Olaia Residences?
- Olaia Residences was 14% built at the site inspection on 21 July 2026. The site has been inspected 4 times since February 2025. The Land Department took 25 site photos at its inspections.
- Is Olaia Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Olaia Residences?
- The registered developer is Gulf House Real Estate Development.
- Which bank holds the escrow account for Olaia Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.