Eome construction progress

The register lists Eome in Palm Jumeirah as complete, with a registered completion date of November 2024. Its last site inspection on record was in June 2026. The developer is Blue Haven Real Estate Development.

100%

Built, at the site inspection of 10 June 2026

Construction complete

Registered completion date
November 2024
Construction started
February 2023
First registered
March 2023
Developer
Blue Haven Real Estate Development
Community
Palm Jumeirah
Units
26
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ايومي
Project number
2580
Site inspections
8

Schedule

The register lists Eome as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 June 2026

100%+1.3 pts

  • Eome construction site, inspection photo 1, 10 June 2026
  • Eome construction site, inspection photo 2, 10 June 2026
  • Eome construction site, inspection photo 3, 10 June 2026
  • Eome construction site, inspection photo 4, 10 June 2026

26 January 2026

99%+0.1 pts

  • Eome construction site, inspection photo 1, 26 January 2026
  • Eome construction site, inspection photo 2, 26 January 2026
  • Eome construction site, inspection photo 3, 26 January 2026
  • Eome construction site, inspection photo 4, 26 January 2026

11 December 2025

99%+0.2 pts

  • Eome construction site, inspection photo 1, 11 December 2025
  • Eome construction site, inspection photo 2, 11 December 2025
  • Eome construction site, inspection photo 3, 11 December 2025
  • Eome construction site, inspection photo 4, 11 December 2025

11 August 2025

98%+17 pts

  • Eome construction site, inspection photo 1, 11 August 2025
  • Eome construction site, inspection photo 2, 11 August 2025
  • Eome construction site, inspection photo 3, 11 August 2025
  • Eome construction site, inspection photo 4, 11 August 2025

18 April 2025

81%+61 pts

  • Eome construction site, inspection photo 1, 18 April 2025
  • Eome construction site, inspection photo 2, 18 April 2025
  • Eome construction site, inspection photo 3, 18 April 2025
  • Eome construction site, inspection photo 4, 18 April 2025

23 April 2024

20%+17 pts

  • Eome construction site, inspection photo 1, 23 April 2024
  • Eome construction site, inspection photo 2, 23 April 2024
  • Eome construction site, inspection photo 3, 23 April 2024
  • Eome construction site, inspection photo 4, 23 April 2024

3 August 2023

3.1%+3.1 pts

  • Eome construction site, inspection photo 1, 3 August 2023
  • Eome construction site, inspection photo 2, 3 August 2023
  • Eome construction site, inspection photo 3, 3 August 2023
  • Eome construction site, inspection photo 4, 3 August 2023

16 February 2023

0%

  • Eome construction site, inspection photo 1, 16 February 2023
  • Eome construction site, inspection photo 2, 16 February 2023

All 67 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in Eome?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Eome handover date?
Construction of Eome is recorded as complete, with a registered completion date of November 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Eome?
Eome was 100% built at the site inspection on 10 June 2026. The site has been inspected 8 times since February 2023. The Land Department took 67 site photos at its inspections.
Is Eome delayed?
The register lists construction as complete.
Who is building Eome?
The registered developer is Blue Haven Real Estate Development.
Which bank holds the escrow account for Eome?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.