Ellington Beach House construction progress

The register lists Ellington Beach House in Palm Jumeirah as complete, with a registered completion date of July 2024. Its last site inspection on record was in December 2024. The developer is Beach House Real Estate Development.

100%

Built, at the site inspection of 24 December 2024

Construction complete

Registered completion date
July 2024
Construction started
July 2022
First registered
September 2022
Developer
Beach House Real Estate Development
Community
Palm Jumeirah
Units
350
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
إلينغتون بيتش هاوس
Project number
2437
Site inspections
7

Schedule

The register lists Ellington Beach House as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 December 2024

100%+4.9 pts

  • Ellington Beach House construction site, inspection photo 1, 24 December 2024
  • Ellington Beach House construction site, inspection photo 2, 24 December 2024
  • Ellington Beach House construction site, inspection photo 3, 24 December 2024
  • Ellington Beach House construction site, inspection photo 4, 24 December 2024

23 September 2024

95%+12 pts

  • Ellington Beach House construction site, inspection photo 1, 23 September 2024
  • Ellington Beach House construction site, inspection photo 2, 23 September 2024
  • Ellington Beach House construction site, inspection photo 3, 23 September 2024
  • Ellington Beach House construction site, inspection photo 4, 23 September 2024

13 February 2024

83%+7.7 pts

  • Ellington Beach House construction site, inspection photo 1, 13 February 2024
  • Ellington Beach House construction site, inspection photo 2, 13 February 2024
  • Ellington Beach House construction site, inspection photo 3, 13 February 2024
  • Ellington Beach House construction site, inspection photo 4, 13 February 2024

23 October 2023

75%+23 pts

  • Ellington Beach House construction site, inspection photo 1, 23 October 2023
  • Ellington Beach House construction site, inspection photo 2, 23 October 2023
  • Ellington Beach House construction site, inspection photo 3, 23 October 2023
  • Ellington Beach House construction site, inspection photo 4, 23 October 2023

22 March 2023

52%+8.0 pts

  • Ellington Beach House construction site, inspection photo 1, 22 March 2023
  • Ellington Beach House construction site, inspection photo 2, 22 March 2023
  • Ellington Beach House construction site, inspection photo 3, 22 March 2023
  • Ellington Beach House construction site, inspection photo 4, 22 March 2023

27 January 2023

44%+10 pts

  • Ellington Beach House construction site, inspection photo 1, 27 January 2023
  • Ellington Beach House construction site, inspection photo 2, 27 January 2023
  • Ellington Beach House construction site, inspection photo 3, 27 January 2023
  • Ellington Beach House construction site, inspection photo 4, 27 January 2023

5 August 2022

34%

  • Ellington Beach House construction site, inspection photo 1, 5 August 2022
  • Ellington Beach House construction site, inspection photo 2, 5 August 2022
  • Ellington Beach House construction site, inspection photo 3, 5 August 2022
  • Ellington Beach House construction site, inspection photo 4, 5 August 2022

All 71 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in Ellington Beach House?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ellington Beach House handover date?
Construction of Ellington Beach House is recorded as complete, with a registered completion date of July 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ellington Beach House?
Ellington Beach House was 100% built at the site inspection on 24 December 2024. The site has been inspected 7 times since August 2022. The Land Department took 71 site photos at its inspections.
Is Ellington Beach House delayed?
The register lists construction as complete.
Who is building Ellington Beach House?
The registered developer is Beach House Real Estate Development.
Which bank holds the escrow account for Ellington Beach House?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.