Ava At Palm Jumeirah By Omniyat construction progress
Ava At Palm Jumeirah By Omniyat in Palm Jumeirah is 96% built at the Land Department inspection of August 2026. Developer Ava Residences Real Estate Developments. Completion registered for June 2026.
96%
Built, at the Land Department site inspection of 26 August 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- September 2026
- Construction started
- July 2022
- Registered with the Land Department
- May 2022
- Developer
- Ava Residences Real Estate Developments
- Community
- Palm Jumeirah
- Units
- 17
- Escrow bank
- Ajman Bank
- Name in Arabic
- أفا أت بالم جميرا من أمنيات
- Land Department project number
- 2382
- Land Department site inspections
- 11
Schedule
Ava At Palm Jumeirah By Omniyat was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
26 August 2026
96%+4.9 pts
18 June 2026
91%+11 pts
27 February 2026
80%+21 pts
27 October 2025
59%+16 pts
20 June 2025
43%+8.0 pts
5 February 2025
35%+12 pts
5 December 2024
23%+10 pts
3 July 2024
13%+3.7 pts
25 March 2024
8.9%+4.0 pts
5 June 2023
4.8%+3.5 pts
Context
Palm Jumeirah has 18 projects under construction, 48% built on average.
Own a unit in Ava At Palm Jumeirah By Omniyat?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Ava At Palm Jumeirah By Omniyat be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ava At Palm Jumeirah By Omniyat is built?
- 96%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 11 times since January 2023.
- Is Ava At Palm Jumeirah By Omniyat delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Ava At Palm Jumeirah By Omniyat?
- The registered developer is Ava Residences Real Estate Developments.
- Which bank holds the escrow account for Ava At Palm Jumeirah By Omniyat?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)










.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)