Ava At Palm Jumeirah By Omniyat construction progress

Ava At Palm Jumeirah By Omniyat in Palm Jumeirah is 96% built at the Land Department inspection of August 2026. Developer Ava Residences Real Estate Developments. Completion registered for June 2026.

96%

Built, at the Land Department site inspection of 26 August 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
September 2026
Construction started
July 2022
Registered with the Land Department
May 2022
Developer
Ava Residences Real Estate Developments
Community
Palm Jumeirah
Units
17
Escrow bank
Ajman Bank
Name in Arabic
أفا أت بالم جميرا من أمنيات
Land Department project number
2382
Land Department site inspections
11

Schedule

Ava At Palm Jumeirah By Omniyat was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

26 August 2026

96%+4.9 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 26 August 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 26 August 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 26 August 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 26 August 2026

18 June 2026

91%+11 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 18 June 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 18 June 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 18 June 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 18 June 2026

27 February 2026

80%+21 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 27 February 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 27 February 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 27 February 2026
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 27 February 2026

27 October 2025

59%+16 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 27 October 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 27 October 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 27 October 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 27 October 2025

20 June 2025

43%+8.0 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 20 June 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 20 June 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 20 June 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 20 June 2025

5 February 2025

35%+12 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 5 February 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 5 February 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 5 February 2025
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 5 February 2025

5 December 2024

23%+10 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 5 December 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 5 December 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 5 December 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 5 December 2024

3 July 2024

13%+3.7 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 3 July 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 3 July 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 3 July 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 3 July 2024

25 March 2024

8.9%+4.0 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 25 March 2024
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 25 March 2024

5 June 2023

4.8%+3.5 pts

  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 1, 5 June 2023
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 2, 5 June 2023
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 3, 5 June 2023
  • Ava At Palm Jumeirah By Omniyat construction site, Land Department inspection photo 4, 5 June 2023

All 87 site photos, by inspection date

Context

Palm Jumeirah has 18 projects under construction, 48% built on average.

Own a unit in Ava At Palm Jumeirah By Omniyat?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ava At Palm Jumeirah By Omniyat be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ava At Palm Jumeirah By Omniyat is built?
96%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 11 times since January 2023.
Is Ava At Palm Jumeirah By Omniyat delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Ava At Palm Jumeirah By Omniyat?
The registered developer is Ava Residences Real Estate Developments.
Which bank holds the escrow account for Ava At Palm Jumeirah By Omniyat?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.