Whitecliffs Residences construction progress

Whitecliffs Residences in Palm Deira is 6.5% built at the Land Department inspection of March 2026. Developer Agp Builders Real Estate Development. Completion registered for December 2027.

6.5%

Built, at the Land Department site inspection of 23 March 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
August 2045
Construction started
December 2024
Registered with the Land Department
December 2024
Developer
Agp Builders Real Estate Development
Community
Palm Deira
Units
73
Escrow bank
Emirates NBD
Name in Arabic
سكن المنحدرات البيضاء
Land Department project number
3384
Land Department site inspections
3

Schedule

Between August 2025 and March 2026 the site added about 0.4 points a month. At that rate it would finish around August 2045, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 March 2026

6.5%+3.1 pts

  • Whitecliffs Residences construction site, Land Department inspection photo 1, 23 March 2026
  • Whitecliffs Residences construction site, Land Department inspection photo 2, 23 March 2026
  • Whitecliffs Residences construction site, Land Department inspection photo 3, 23 March 2026
  • Whitecliffs Residences construction site, Land Department inspection photo 4, 23 March 2026

2 August 2025

3.4%+3.4 pts

  • Whitecliffs Residences construction site, Land Department inspection photo 1, 2 August 2025
  • Whitecliffs Residences construction site, Land Department inspection photo 2, 2 August 2025
  • Whitecliffs Residences construction site, Land Department inspection photo 3, 2 August 2025
  • Whitecliffs Residences construction site, Land Department inspection photo 4, 2 August 2025

5 November 2024

0%

  • Whitecliffs Residences construction site, Land Department inspection photo 1, 5 November 2024
  • Whitecliffs Residences construction site, Land Department inspection photo 2, 5 November 2024

All 11 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Whitecliffs Residences is behind that average.

Own a unit in Whitecliffs Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Whitecliffs Residences be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around August 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Whitecliffs Residences is built?
6.5%, measured at the Land Department site inspection on 23 March 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Whitecliffs Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Whitecliffs Residences?
The registered developer is Agp Builders Real Estate Development.
Which bank holds the escrow account for Whitecliffs Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.