Whitecliffs Residences construction progress

The registered completion date for Whitecliffs Residences in Palm Deira is December 2027. At the last site inspection, in October 2026, it was 17% built. The developer is Agp Builders Real Estate Development.

17%

Built, at the site inspection of 26 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
April 2031
Construction started
December 2024
First registered
December 2024
Developer
Agp Builders Real Estate Development
Community
Palm Deira
Units
73
Escrow bank
Emirates NBD
Name in Arabic
سكن المنحدرات البيضاء
Project number
3384
Site inspections
4

Schedule

Between March 2026 and October 2026 the site added about 1.5 points a month. At that rate it would finish around April 2031, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

17%+11 pts

  • Whitecliffs Residences construction site, inspection photo 1, 26 October 2026
  • Whitecliffs Residences construction site, inspection photo 2, 26 October 2026
  • Whitecliffs Residences construction site, inspection photo 3, 26 October 2026
  • Whitecliffs Residences construction site, inspection photo 4, 26 October 2026

23 March 2026

6.5%+3.1 pts

  • Whitecliffs Residences construction site, inspection photo 1, 23 March 2026
  • Whitecliffs Residences construction site, inspection photo 2, 23 March 2026
  • Whitecliffs Residences construction site, inspection photo 3, 23 March 2026
  • Whitecliffs Residences construction site, inspection photo 4, 23 March 2026

2 August 2025

3.4%+3.4 pts

  • Whitecliffs Residences construction site, inspection photo 1, 2 August 2025
  • Whitecliffs Residences construction site, inspection photo 2, 2 August 2025
  • Whitecliffs Residences construction site, inspection photo 3, 2 August 2025
  • Whitecliffs Residences construction site, inspection photo 4, 2 August 2025

5 November 2024

0%

  • Whitecliffs Residences construction site, inspection photo 1, 5 November 2024
  • Whitecliffs Residences construction site, inspection photo 2, 5 November 2024

All 19 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Whitecliffs Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Whitecliffs Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Whitecliffs Residences?
Whitecliffs Residences was 17% built at the site inspection on 26 October 2026. The site has been inspected 4 times since November 2024. The Land Department took 19 site photos at its inspections.
Is Whitecliffs Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Whitecliffs Residences?
The registered developer is Agp Builders Real Estate Development.
Which bank holds the escrow account for Whitecliffs Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.