Wellington Ocean Walk construction progress

Wellington Ocean Walk in Palm Deira is 16% built at the Land Department inspection of July 2026. Developer Wellington Ocean Real Estate Development. Completion registered for December 2028.

16%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
July 2031
Construction started
September 2025
Registered with the Land Department
October 2025
Developer
Wellington Ocean Real Estate Development
Community
Palm Deira
Units
79
Escrow bank
United Bank Limited
Name in Arabic
ممشى ويلينغتون المحيطي
Land Department project number
4026
Land Department site inspections
4

Schedule

Between August 2025 and July 2026 the site added about 1.4 points a month. At that rate it would finish around July 2031, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

16%+3.0 pts

  • Wellington Ocean Walk construction site, Land Department inspection photo 1, 27 July 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 2, 27 July 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 3, 27 July 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 4, 27 July 2026

29 April 2026

13%+8.9 pts

  • Wellington Ocean Walk construction site, Land Department inspection photo 1, 29 April 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 2, 29 April 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 3, 29 April 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 4, 29 April 2026

26 January 2026

4.0%+4.0 pts

  • Wellington Ocean Walk construction site, Land Department inspection photo 1, 26 January 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 2, 26 January 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 3, 26 January 2026
  • Wellington Ocean Walk construction site, Land Department inspection photo 4, 26 January 2026

19 August 2025

0%

  • Wellington Ocean Walk construction site, Land Department inspection photo 1, 19 August 2025
  • Wellington Ocean Walk construction site, Land Department inspection photo 2, 19 August 2025

All 19 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Wellington Ocean Walk is behind that average.

Own a unit in Wellington Ocean Walk?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Wellington Ocean Walk be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around July 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Wellington Ocean Walk is built?
16%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 4 times since August 2025.
Is Wellington Ocean Walk delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Wellington Ocean Walk?
The registered developer is Wellington Ocean Real Estate Development.
Which bank holds the escrow account for Wellington Ocean Walk?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.