Wellington Ocean Walk construction progress

The registered completion date for Wellington Ocean Walk in Palm Deira is December 2028. At the last site inspection, in October 2026, it was 21% built. The developer is Wellington Ocean Real Estate Development.

21%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
April 2030
Construction started
September 2025
First registered
October 2025
Developer
Wellington Ocean Real Estate Development
Community
Palm Deira
Units
79
Escrow bank
United Bank Limited
Name in Arabic
ممشى ويلينغتون المحيطي
Project number
4026
Site inspections
5

Schedule

Between January 2026 and October 2026 the site added about 1.9 points a month. At that rate it would finish around April 2030, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

21%+4.9 pts

  • Wellington Ocean Walk construction site, inspection photo 1, 22 October 2026
  • Wellington Ocean Walk construction site, inspection photo 2, 22 October 2026
  • Wellington Ocean Walk construction site, inspection photo 3, 22 October 2026
  • Wellington Ocean Walk construction site, inspection photo 4, 22 October 2026

27 July 2026

16%+3.0 pts

  • Wellington Ocean Walk construction site, inspection photo 1, 27 July 2026
  • Wellington Ocean Walk construction site, inspection photo 2, 27 July 2026
  • Wellington Ocean Walk construction site, inspection photo 3, 27 July 2026
  • Wellington Ocean Walk construction site, inspection photo 4, 27 July 2026

29 April 2026

13%+8.9 pts

  • Wellington Ocean Walk construction site, inspection photo 1, 29 April 2026
  • Wellington Ocean Walk construction site, inspection photo 2, 29 April 2026
  • Wellington Ocean Walk construction site, inspection photo 3, 29 April 2026
  • Wellington Ocean Walk construction site, inspection photo 4, 29 April 2026

26 January 2026

4.0%+4.0 pts

  • Wellington Ocean Walk construction site, inspection photo 1, 26 January 2026
  • Wellington Ocean Walk construction site, inspection photo 2, 26 January 2026
  • Wellington Ocean Walk construction site, inspection photo 3, 26 January 2026
  • Wellington Ocean Walk construction site, inspection photo 4, 26 January 2026

19 August 2025

0%

  • Wellington Ocean Walk construction site, inspection photo 1, 19 August 2025
  • Wellington Ocean Walk construction site, inspection photo 2, 19 August 2025

All 26 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Wellington Ocean Walk?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Wellington Ocean Walk handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Wellington Ocean Walk?
Wellington Ocean Walk was 21% built at the site inspection on 22 October 2026. The site has been inspected 5 times since August 2025. The Land Department took 26 site photos at its inspections.
Is Wellington Ocean Walk delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Wellington Ocean Walk?
The registered developer is Wellington Ocean Real Estate Development.
Which bank holds the escrow account for Wellington Ocean Walk?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.