Villa Del Gavi Residences construction progress

Villa Del Gavi Residences in Palm Deira is 38% built at the Land Department inspection of September 2026. Developer Mr Eight Real Estate Development. Completion registered for December 2027.

38%

Built, at the Land Department site inspection of 28 September 2026

On pace for its date

Completion date (Land Department)
December 2027
Finish at recent pace
September 2027
Construction started
September 2025
Registered with the Land Department
July 2025
Developer
Mr Eight Real Estate Development
Community
Palm Deira
Units
87
Escrow bank
Bank of Sharjah
Name in Arabic
فيلا ديل جافي رزيدينسز
Land Department project number
3751
Land Department site inspections
4

Schedule

Since March 2026 Villa Del Gavi Residences has added about 5.5 points a month. That puts 100% around September 2027, within three months of its registered completion date of December 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 September 2026

38%+22 pts

  • Villa Del Gavi Residences construction site, Land Department inspection photo 1, 28 September 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 2, 28 September 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 3, 28 September 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 4, 28 September 2026

8 July 2026

16%+12 pts

  • Villa Del Gavi Residences construction site, Land Department inspection photo 1, 8 July 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 2, 8 July 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 3, 8 July 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 4, 8 July 2026

25 March 2026

3.7%+3.7 pts

  • Villa Del Gavi Residences construction site, Land Department inspection photo 1, 25 March 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 2, 25 March 2026
  • Villa Del Gavi Residences construction site, Land Department inspection photo 3, 25 March 2026

16 June 2025

0%

  • Villa Del Gavi Residences construction site, Land Department inspection photo 1, 16 June 2025
  • Villa Del Gavi Residences construction site, Land Department inspection photo 2, 16 June 2025

All 23 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Villa Del Gavi Residences is ahead of that average.

Own a unit in Villa Del Gavi Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Villa Del Gavi Residences be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Villa Del Gavi Residences is built?
38%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 4 times since June 2025.
Is Villa Del Gavi Residences delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
Who is building Villa Del Gavi Residences?
The registered developer is Mr Eight Real Estate Development.
Which bank holds the escrow account for Villa Del Gavi Residences?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.