Villa Del Gavi Residences construction progress

The registered completion date for Villa Del Gavi Residences in Palm Deira is December 2027. At the last site inspection, in September 2026, it was 38% built. The developer is Mr Eight Real Estate Development.

38%

Built, at the site inspection of 28 September 2026

On pace for its date

Registered completion date
December 2027
Finish at recent pace
September 2027
Construction started
September 2025
First registered
July 2025
Developer
Mr Eight Real Estate Development
Community
Palm Deira
Units
87
Escrow bank
Bank of Sharjah
Name in Arabic
فيلا ديل جافي رزيدينسز
Project number
3751
Site inspections
4

Schedule

Since March 2026 Villa Del Gavi Residences has added about 5.5 points a month. That puts 100% around September 2027, within three months of its registered completion date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 September 2026

38%+22 pts

  • Villa Del Gavi Residences construction site, inspection photo 1, 28 September 2026
  • Villa Del Gavi Residences construction site, inspection photo 2, 28 September 2026
  • Villa Del Gavi Residences construction site, inspection photo 3, 28 September 2026
  • Villa Del Gavi Residences construction site, inspection photo 4, 28 September 2026

8 July 2026

16%+12 pts

  • Villa Del Gavi Residences construction site, inspection photo 1, 8 July 2026
  • Villa Del Gavi Residences construction site, inspection photo 2, 8 July 2026
  • Villa Del Gavi Residences construction site, inspection photo 3, 8 July 2026
  • Villa Del Gavi Residences construction site, inspection photo 4, 8 July 2026

25 March 2026

3.7%+3.7 pts

  • Villa Del Gavi Residences construction site, inspection photo 1, 25 March 2026
  • Villa Del Gavi Residences construction site, inspection photo 2, 25 March 2026
  • Villa Del Gavi Residences construction site, inspection photo 3, 25 March 2026

16 June 2025

0%

  • Villa Del Gavi Residences construction site, inspection photo 1, 16 June 2025
  • Villa Del Gavi Residences construction site, inspection photo 2, 16 June 2025

All 23 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Villa Del Gavi Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Villa Del Gavi Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Villa Del Gavi Residences?
Villa Del Gavi Residences was 38% built at the site inspection on 28 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 23 site photos at its inspections.
Is Villa Del Gavi Residences delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
Who is building Villa Del Gavi Residences?
The registered developer is Mr Eight Real Estate Development.
Which bank holds the escrow account for Villa Del Gavi Residences?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.