Villa Del Gavi Residences construction progress
Villa Del Gavi Residences in Palm Deira is 38% built at the Land Department inspection of September 2026. Developer Mr Eight Real Estate Development. Completion registered for December 2027.
38%
Built, at the Land Department site inspection of 28 September 2026
On pace for its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- September 2027
- Construction started
- September 2025
- Registered with the Land Department
- July 2025
- Developer
- Mr Eight Real Estate Development
- Community
- Palm Deira
- Units
- 87
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- فيلا ديل جافي رزيدينسز
- Land Department project number
- 3751
- Land Department site inspections
- 4
Schedule
Since March 2026 Villa Del Gavi Residences has added about 5.5 points a month. That puts 100% around September 2027, within three months of its registered completion date of December 2027.
Site inspections
28 September 2026
38%+22 pts
8 July 2026
16%+12 pts
25 March 2026
3.7%+3.7 pts
16 June 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average. Villa Del Gavi Residences is ahead of that average.
Own a unit in Villa Del Gavi Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Villa Del Gavi Residences be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Villa Del Gavi Residences is built?
- 38%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 4 times since June 2025.
- Is Villa Del Gavi Residences delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
- Who is building Villa Del Gavi Residences?
- The registered developer is Mr Eight Real Estate Development.
- Which bank holds the escrow account for Villa Del Gavi Residences?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.