Vayla Residences construction progress

Vayla Residences in Palm Deira was registered to complete in July 2026 and is still under construction. At the last site inspection, in April 2026, it was 22% built. The developer is Blue Square Real Estate Development.

40%

Built, at the site inspection of 6 April 2026

4 months past its registered completion date

Registered completion date
July 2026
Finish at recent pace
April 2029
Construction started
April 2025
First registered
November 2025
Developer
Blue Square Real Estate Development
Community
Palm Deira
Units
53
Escrow bank
The National Bank of Fujairah
Name in Arabic
فايلا ريزيدنسز
Project number
4080
Site inspections
2

Schedule

Vayla Residences was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around April 2029.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 April 2026

22%+13 pts

  • Vayla Residences construction site, inspection photo 1, 6 April 2026
  • Vayla Residences construction site, inspection photo 2, 6 April 2026
  • Vayla Residences construction site, inspection photo 3, 6 April 2026
  • Vayla Residences construction site, inspection photo 4, 6 April 2026

30 September 2025

8.9%

  • Vayla Residences construction site, inspection photo 1, 30 September 2025
  • Vayla Residences construction site, inspection photo 2, 30 September 2025
  • Vayla Residences construction site, inspection photo 3, 30 September 2025
  • Vayla Residences construction site, inspection photo 4, 30 September 2025

All 12 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Vayla Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vayla Residences handover date?
The registered completion date was July 2026, and the register still lists Vayla Residences as under construction. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vayla Residences?
Vayla Residences was 40% built at the site inspection on 6 April 2026. The site has been inspected 2 times since September 2025. The Land Department took 12 site photos at its inspections.
Is Vayla Residences delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building Vayla Residences?
The registered developer is Blue Square Real Estate Development.
Which bank holds the escrow account for Vayla Residences?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.