Vayla Residences construction progress

Vayla Residences in Palm Deira is 22% built at the Land Department inspection of April 2026. Developer Blue Square Real Estate Development. Completion registered for July 2026.

22%

Built, at the Land Department site inspection of 6 April 2026

3 months past its registered completion date

Completion date (Land Department)
July 2026
Finish at recent pace
April 2029
Construction started
April 2025
Registered with the Land Department
November 2025
Developer
Blue Square Real Estate Development
Community
Palm Deira
Units
53
Escrow bank
The National Bank of Fujairah
Name in Arabic
فايلا ريزيدنسز
Land Department project number
4080
Land Department site inspections
2

Schedule

Vayla Residences was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around April 2029.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 April 2026

22%+13 pts

  • Vayla Residences construction site, Land Department inspection photo 1, 6 April 2026
  • Vayla Residences construction site, Land Department inspection photo 2, 6 April 2026
  • Vayla Residences construction site, Land Department inspection photo 3, 6 April 2026
  • Vayla Residences construction site, Land Department inspection photo 4, 6 April 2026

30 September 2025

8.9%

  • Vayla Residences construction site, Land Department inspection photo 1, 30 September 2025
  • Vayla Residences construction site, Land Department inspection photo 2, 30 September 2025
  • Vayla Residences construction site, Land Department inspection photo 3, 30 September 2025
  • Vayla Residences construction site, Land Department inspection photo 4, 30 September 2025

All 12 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Vayla Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vayla Residences be completed?
The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vayla Residences is built?
22%, measured at the Land Department site inspection on 6 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Vayla Residences delayed?
Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
Who is building Vayla Residences?
The registered developer is Blue Square Real Estate Development.
Which bank holds the escrow account for Vayla Residences?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.