Tomorrow 166 construction progress

Tomorrow 166 in Palm Deira is 1.7% built at the Land Department inspection of April 2026. Developer Tomorrow World Real Estate Development. Completion registered for May 2027.

1.7%

Built, at the Land Department site inspection of 1 April 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
October 2083
Construction started
June 2025
Registered with the Land Department
May 2025
Community
Palm Deira
Units
54
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
غدا 166
Land Department project number
3638
Land Department site inspections
2

Schedule

Between April 2025 and April 2026 the site added about 0.1 points a month. At that rate it would finish around October 2083, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 April 2026

1.7%+1.7 pts

  • Tomorrow 166 construction site, Land Department inspection photo 1, 1 April 2026
  • Tomorrow 166 construction site, Land Department inspection photo 2, 1 April 2026

7 April 2025

0%

  • Tomorrow 166 construction site, Land Department inspection photo 1, 7 April 2025

All 3 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Tomorrow 166 is behind that average.

Tomorrow World Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Tomorrow 166?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Tomorrow 166 be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around October 2083. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Tomorrow 166 is built?
1.7%, measured at the Land Department site inspection on 1 April 2026. The Land Department engineers have inspected the site 2 times since April 2025.
Is Tomorrow 166 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Tomorrow 166?
The registered developer is Tomorrow World Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Tomorrow 166?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.