Seaside By Prestige One construction progress
The registered completion date for Seaside By Prestige One in Palm Deira is December 2026. At the last site inspection, in November 2026, it was 53% built. The developer is Prestige The Seaside Real Estate Development.
53%
Built, at the site inspection of 2 November 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- December 2027
- Construction started
- July 2024
- First registered
- July 2024
- Developer
- Prestige The Seaside Real Estate Development
- Community
- Palm Deira
- Units
- 121
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سي سايد من بريستيج
- Project number
- 3119
- Site inspections
- 7
Schedule
Between January 2026 and November 2026 the site added about 3.6 points a month. At that rate it would finish around December 2027, more than three months after its registered date of December 2026.
Site inspections
2 November 2026
53%+10.0 pts
30 July 2026
43%+9.7 pts
30 April 2026
33%+13 pts
29 January 2026
20%+14 pts
30 May 2025
5.7%+5.6 pts
13 December 2024
0%+0.0 pts
6 June 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Seaside By Prestige One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Seaside By Prestige One handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Seaside By Prestige One?
- Seaside By Prestige One was 53% built at the site inspection on 2 November 2026. The site has been inspected 7 times since June 2024. The Land Department took 43 site photos at its inspections.
- Is Seaside By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Seaside By Prestige One?
- The registered developer is Prestige The Seaside Real Estate Development.
- Which bank holds the escrow account for Seaside By Prestige One?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.













.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)