Sea View Residence By Sama Mayas construction progress

The registered completion date for Sea View Residence By Sama Mayas in Palm Deira is September 2027. At the last site inspection, in June 2026, it was 13% built. The developer is Sama Mayas Real Estate Development.

19%

Built, at the site inspection of 1 June 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
August 2036
Construction started
April 2025
First registered
August 2025
Developer
Sama Mayas Real Estate Development
Community
Palm Deira
Units
63
Escrow bank
Zand Bank
Name in Arabic
سي فيو ريزيدنس من سما مياس
Project number
3721
Site inspections
3

Schedule

Between February 2026 and June 2026 the site added about 0.7 points a month. At that rate it would finish around August 2036, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 June 2026

13%+2.5 pts

  • Sea View Residence By Sama Mayas construction site, inspection photo 1, 1 June 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 2, 1 June 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 3, 1 June 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 4, 1 June 2026

16 February 2026

10%+9.8 pts

  • Sea View Residence By Sama Mayas construction site, inspection photo 1, 16 February 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 2, 16 February 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 3, 16 February 2026
  • Sea View Residence By Sama Mayas construction site, inspection photo 4, 16 February 2026

28 April 2025

0.4%

  • Sea View Residence By Sama Mayas construction site, inspection photo 1, 28 April 2025
  • Sea View Residence By Sama Mayas construction site, inspection photo 2, 28 April 2025
  • Sea View Residence By Sama Mayas construction site, inspection photo 3, 28 April 2025
  • Sea View Residence By Sama Mayas construction site, inspection photo 4, 28 April 2025

All 15 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Sea View Residence By Sama Mayas?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sea View Residence By Sama Mayas handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sea View Residence By Sama Mayas?
Sea View Residence By Sama Mayas was 19% built at the site inspection on 1 June 2026. The site has been inspected 3 times since April 2025. The Land Department took 15 site photos at its inspections.
Is Sea View Residence By Sama Mayas delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Sea View Residence By Sama Mayas?
The registered developer is Sama Mayas Real Estate Development.
Which bank holds the escrow account for Sea View Residence By Sama Mayas?
Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.