Sea Coral By Next Realty construction progress

The registered completion date for Sea Coral By Next Realty in Palm Deira is August 2027. At the last site inspection, in October 2026, it was 11% built. The developer is Next Realty Real Estate.

11%

Built, at the site inspection of 2 October 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
February 2034
Construction started
August 2024
First registered
April 2025
Developer
Next Realty Real Estate
Community
Palm Deira
Units
80
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
سي كورال من نيكست رياليتي
Project number
3062
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around February 2034, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 October 2026

11%+5.2 pts

  • Sea Coral By Next Realty construction site, inspection photo 1, 2 October 2026
  • Sea Coral By Next Realty construction site, inspection photo 2, 2 October 2026
  • Sea Coral By Next Realty construction site, inspection photo 3, 2 October 2026
  • Sea Coral By Next Realty construction site, inspection photo 4, 2 October 2026

28 April 2026

5.5%+5.5 pts

  • Sea Coral By Next Realty construction site, inspection photo 1, 28 April 2026
  • Sea Coral By Next Realty construction site, inspection photo 2, 28 April 2026
  • Sea Coral By Next Realty construction site, inspection photo 3, 28 April 2026
  • Sea Coral By Next Realty construction site, inspection photo 4, 28 April 2026

23 May 2024

0%

  • Sea Coral By Next Realty construction site, inspection photo 1, 23 May 2024
  • Sea Coral By Next Realty construction site, inspection photo 2, 23 May 2024

All 11 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Sea Coral By Next Realty?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sea Coral By Next Realty handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sea Coral By Next Realty?
Sea Coral By Next Realty was 11% built at the site inspection on 2 October 2026. The site has been inspected 3 times since May 2024. The Land Department took 11 site photos at its inspections.
Is Sea Coral By Next Realty delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Sea Coral By Next Realty?
The registered developer is Next Realty Real Estate.
Which bank holds the escrow account for Sea Coral By Next Realty?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.