Royal Yacht Club Residence construction progress
The registered completion date for Royal Yacht Club Residence in Palm Deira is November 2027. At the last site inspection, in October 2026, it was 25% built. The developer is Azimuth Development.
25%
Built, at the site inspection of 20 October 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- March 2029
- Construction started
- May 2025
- First registered
- November 2025
- Developer
- Azimuth Development
- Community
- Palm Deira
- Units
- 147
- Escrow bank
- Emirates NBD
- Name in Arabic
- رويال ياتش كلوب ريزيدنس
- Project number
- 3770
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 2.6 points a month. At that rate it would finish around March 2029, more than three months after its registered date of November 2027.
Site inspections
20 October 2026
25%+11 pts
18 June 2026
15%+12 pts
8 July 2025
3.1%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Royal Yacht Club Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Royal Yacht Club Residence handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Royal Yacht Club Residence?
- Royal Yacht Club Residence was 25% built at the site inspection on 20 October 2026. The site has been inspected 3 times since July 2025. The Land Department took 19 site photos at its inspections.
- Is Royal Yacht Club Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Royal Yacht Club Residence?
- The registered developer is Azimuth Development.
- Which bank holds the escrow account for Royal Yacht Club Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.