Royal Yacht Club Residence construction progress

Royal Yacht Club Residence in Palm Deira is 15% built at the Land Department inspection of June 2026. Developer Azimuth Development. Completion registered for November 2027.

15%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
June 2033
Construction started
May 2025
Registered with the Land Department
November 2025
Developer
Azimuth Development
Community
Palm Deira
Units
147
Escrow bank
Emirates NBD
Name in Arabic
رويال ياتش كلوب ريزيدنس
Land Department project number
3770
Land Department site inspections
2

Schedule

Between July 2025 and June 2026 the site added about 1.0 points a month. At that rate it would finish around June 2033, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

15%+12 pts

  • Royal Yacht Club Residence construction site, Land Department inspection photo 1, 18 June 2026
  • Royal Yacht Club Residence construction site, Land Department inspection photo 2, 18 June 2026
  • Royal Yacht Club Residence construction site, Land Department inspection photo 3, 18 June 2026
  • Royal Yacht Club Residence construction site, Land Department inspection photo 4, 18 June 2026

8 July 2025

3.1%

  • Royal Yacht Club Residence construction site, Land Department inspection photo 1, 8 July 2025
  • Royal Yacht Club Residence construction site, Land Department inspection photo 2, 8 July 2025
  • Royal Yacht Club Residence construction site, Land Department inspection photo 3, 8 July 2025
  • Royal Yacht Club Residence construction site, Land Department inspection photo 4, 8 July 2025

All 9 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Royal Yacht Club Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Royal Yacht Club Residence be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around June 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Royal Yacht Club Residence is built?
15%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 2 times since July 2025.
Is Royal Yacht Club Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Royal Yacht Club Residence?
The registered developer is Azimuth Development.
Which bank holds the escrow account for Royal Yacht Club Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.