Octa Isle Interiors By Missoni construction progress
The registered completion date for Octa Isle Interiors By Missoni in Palm Deira is September 2027. At the last site inspection, in September 2026, it was 6.2% built. The developer is Octa Di Development Co.
6.2%
Built, at the site inspection of 1 September 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- January 2035
- Construction started
- August 2025
- First registered
- August 2025
- Developer
- Octa Di Development Co
- Community
- Palm Deira
- Units
- 112
- Escrow bank
- Emirates NBD
- Name in Arabic
- أوكتا آيل تصاميم داخلية من ميسوني
- Project number
- 3793
- Site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 0.9 points a month. At that rate it would finish around January 2035, more than three months after its registered date of September 2027.
Site inspections
1 September 2026
6.2%+2.9 pts
21 May 2026
3.4%+3.1 pts
16 February 2026
0.2%+0.2 pts
27 May 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Octa Isle Interiors By Missoni?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Octa Isle Interiors By Missoni handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Octa Isle Interiors By Missoni?
- Octa Isle Interiors By Missoni was 6.2% built at the site inspection on 1 September 2026. The site has been inspected 4 times since May 2025. The Land Department took 15 site photos at its inspections.
- Is Octa Isle Interiors By Missoni delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Octa Isle Interiors By Missoni?
- The registered developer is Octa Di Development Co.
- Which bank holds the escrow account for Octa Isle Interiors By Missoni?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.