Marea construction progress

The registered completion date for Marea in Palm Deira is June 2027. At the last site inspection, in September 2026, it was 5.3% built. The developer is Sharafi Real Estate Development.

5.3%

Built, at the site inspection of 16 September 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
October 2058
Construction started
July 2025
First registered
October 2025
Developer
Sharafi Real Estate Development
Community
Palm Deira
Units
68
Escrow bank
Emirates NBD
Name in Arabic
ماريا
Project number
3879
Site inspections
4

Schedule

Between February 2026 and September 2026 the site added about 0.2 points a month. At that rate it would finish around October 2058, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 September 2026

5.3%

  • Marea construction site, inspection photo 1, 16 September 2026
  • Marea construction site, inspection photo 2, 16 September 2026
  • Marea construction site, inspection photo 3, 16 September 2026
  • Marea construction site, inspection photo 4, 16 September 2026

10 June 2026

5.3%+1.8 pts

  • Marea construction site, inspection photo 1, 10 June 2026
  • Marea construction site, inspection photo 2, 10 June 2026
  • Marea construction site, inspection photo 3, 10 June 2026
  • Marea construction site, inspection photo 4, 10 June 2026

4 February 2026

3.5%+3.5 pts

  • Marea construction site, inspection photo 1, 4 February 2026
  • Marea construction site, inspection photo 2, 4 February 2026
  • Marea construction site, inspection photo 3, 4 February 2026
  • Marea construction site, inspection photo 4, 4 February 2026

4 August 2025

0%

  • Marea construction site, inspection photo 1, 4 August 2025
  • Marea construction site, inspection photo 2, 4 August 2025

All 17 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Marea?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Marea handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2058. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Marea?
Marea was 5.3% built at the site inspection on 16 September 2026. The site has been inspected 4 times since August 2025. The Land Department took 17 site photos at its inspections.
Is Marea delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Marea?
The registered developer is Sharafi Real Estate Development.
Which bank holds the escrow account for Marea?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.