Luzora Residences construction progress

The registered completion date for Luzora Residences in Palm Deira is January 2027. At the last site inspection, in November 2026, it was 44% built. The developer is D I A Homes Real Estate Development.

44%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
December 2027
Construction started
March 2025
First registered
May 2025
Developer
D I A Homes Real Estate Development
Community
Palm Deira
Units
108
Escrow bank
Emirates NBD
Name in Arabic
لوزورا ريزيدنسز
Project number
3620
Site inspections
5

Schedule

Between January 2026 and November 2026 the site added about 4.3 points a month. At that rate it would finish around December 2027, more than three months after its registered date of January 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

44%+22 pts

  • Luzora Residences construction site, inspection photo 1, 9 November 2026
  • Luzora Residences construction site, inspection photo 2, 9 November 2026
  • Luzora Residences construction site, inspection photo 3, 9 November 2026
  • Luzora Residences construction site, inspection photo 4, 9 November 2026

9 July 2026

21%+12 pts

  • Luzora Residences construction site, inspection photo 1, 9 July 2026
  • Luzora Residences construction site, inspection photo 2, 9 July 2026
  • Luzora Residences construction site, inspection photo 3, 9 July 2026
  • Luzora Residences construction site, inspection photo 4, 9 July 2026

29 April 2026

9.0%+5.5 pts

  • Luzora Residences construction site, inspection photo 1, 29 April 2026
  • Luzora Residences construction site, inspection photo 2, 29 April 2026
  • Luzora Residences construction site, inspection photo 3, 29 April 2026
  • Luzora Residences construction site, inspection photo 4, 29 April 2026

29 January 2026

3.5%+3.5 pts

  • Luzora Residences construction site, inspection photo 1, 29 January 2026
  • Luzora Residences construction site, inspection photo 2, 29 January 2026
  • Luzora Residences construction site, inspection photo 3, 29 January 2026
  • Luzora Residences construction site, inspection photo 4, 29 January 2026

27 March 2025

0%

  • Luzora Residences construction site, inspection photo 1, 27 March 2025
  • Luzora Residences construction site, inspection photo 2, 27 March 2025

All 34 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Luzora Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Luzora Residences handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Luzora Residences?
Luzora Residences was 44% built at the site inspection on 9 November 2026. The site has been inspected 5 times since March 2025. The Land Department took 34 site photos at its inspections.
Is Luzora Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Luzora Residences?
The registered developer is D I A Homes Real Estate Development.
Which bank holds the escrow account for Luzora Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.