Skip to content

Isolana Residences construction progress

Isolana Residences in Palm Deira is 5.5% built at the Land Department inspection of July 2026. Developer Hayaat Ikhlaq Developments. Completion registered for March 2027.

5.5%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
August 2033
Construction started
May 2025
Registered with the Land Department
April 2025
Developer
Hayaat Ikhlaq Developments
Community
Palm Deira
Units
73
Escrow bank
Emirates Islamic Bank
Name in Arabic
إيزولانا ريزيدنسز
Land Department project number
3640
Land Department site inspections
3

Schedule

Between April 2026 and July 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

5.5%+4.1 pts

  • Isolana Residences construction site, Land Department inspection photo 1, 23 July 2026
  • Isolana Residences construction site, Land Department inspection photo 2, 23 July 2026
  • Isolana Residences construction site, Land Department inspection photo 3, 23 July 2026
  • Isolana Residences construction site, Land Department inspection photo 4, 23 July 2026

2 April 2026

1.4%+1.4 pts

  • Isolana Residences construction site, Land Department inspection photo 1, 2 April 2026
  • Isolana Residences construction site, Land Department inspection photo 2, 2 April 2026
  • Isolana Residences construction site, Land Department inspection photo 3, 2 April 2026
  • Isolana Residences construction site, Land Department inspection photo 4, 2 April 2026

3 April 2025

0%

  • Isolana Residences construction site, Land Department inspection photo 1, 3 April 2025
  • Isolana Residences construction site, Land Department inspection photo 2, 3 April 2025

All 12 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Isolana Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Isolana Residences be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around August 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Isolana Residences is built?
5.5%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 3 times since April 2025.
Is Isolana Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Isolana Residences?
The registered developer is Hayaat Ikhlaq Developments.
Which bank holds the escrow account for Isolana Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.