Iluka Residences construction progress

Iluka Residences in Palm Deira was registered to complete in August 2026 and is still under construction. At the last site inspection, in October 2026, it was 57% built. The developer is Ms Homes Developers.

57%

Built, at the site inspection of 15 October 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
November 2027
Construction started
May 2024
First registered
June 2024
Developer
Ms Homes Developers
Community
Palm Deira
Units
57
Escrow bank
United Bank Limited
Name in Arabic
مساكن إيلوكا
Project number
3042
Site inspections
4

Schedule

Iluka Residences was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around November 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

57%+21 pts

  • Iluka Residences construction site, inspection photo 1, 15 October 2026
  • Iluka Residences construction site, inspection photo 2, 15 October 2026
  • Iluka Residences construction site, inspection photo 3, 15 October 2026
  • Iluka Residences construction site, inspection photo 4, 15 October 2026

7 April 2026

36%+23 pts

  • Iluka Residences construction site, inspection photo 1, 7 April 2026
  • Iluka Residences construction site, inspection photo 2, 7 April 2026
  • Iluka Residences construction site, inspection photo 3, 7 April 2026
  • Iluka Residences construction site, inspection photo 4, 7 April 2026

12 August 2025

13%+13 pts

  • Iluka Residences construction site, inspection photo 1, 12 August 2025
  • Iluka Residences construction site, inspection photo 2, 12 August 2025
  • Iluka Residences construction site, inspection photo 3, 12 August 2025
  • Iluka Residences construction site, inspection photo 4, 12 August 2025

28 May 2024

0%

  • Iluka Residences construction site, inspection photo 1, 28 May 2024
  • Iluka Residences construction site, inspection photo 2, 28 May 2024

All 26 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Iluka Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Iluka Residences handover date?
The registered completion date was August 2026, and the register still lists Iluka Residences as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Iluka Residences?
Iluka Residences was 57% built at the site inspection on 15 October 2026. The site has been inspected 4 times since May 2024. The Land Department took 26 site photos at its inspections.
Is Iluka Residences delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building Iluka Residences?
The registered developer is Ms Homes Developers.
Which bank holds the escrow account for Iluka Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.