House Of Well construction progress

The registered completion date for House Of Well in Palm Deira is May 2027. At the last site inspection, in June 2026, it was 6.7% built. The developer is Well Concept Real Estate Development.

6.7%

Built, at the site inspection of 24 June 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
June 2037
Construction started
September 2025
First registered
October 2025
Developer
Well Concept Real Estate Development
Community
Palm Deira
Units
77
Escrow bank
United Bank Limited
Name in Arabic
هاوس أوف ويل
Project number
4072
Site inspections
2

Schedule

Between September 2025 and June 2026 the site added about 0.7 points a month. At that rate it would finish around June 2037, more than three months after its registered date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 June 2026

6.7%+6.7 pts

  • House Of Well construction site, inspection photo 1, 24 June 2026
  • House Of Well construction site, inspection photo 2, 24 June 2026
  • House Of Well construction site, inspection photo 3, 24 June 2026
  • House Of Well construction site, inspection photo 4, 24 June 2026

11 September 2025

0%

  • House Of Well construction site, inspection photo 1, 11 September 2025
  • House Of Well construction site, inspection photo 2, 11 September 2025

All 7 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in House Of Well?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the House Of Well handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on House Of Well?
House Of Well was 6.7% built at the site inspection on 24 June 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
Is House Of Well delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building House Of Well?
The registered developer is Well Concept Real Estate Development.
Which bank holds the escrow account for House Of Well?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.