Skip to content

Flora Shore By Calgary Properties construction progress

The registered completion date for Flora Shore By Calgary Properties in Palm Deira is September 2027. At the last site inspection, in July 2026, it was 2.2% built. The developer is Calgary Properties.

2.2%

Built, at the site inspection of 8 July 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
July 2042
Construction started
November 2025
First registered
August 2025
Developer
Calgary Properties
Community
Palm Deira
Units
76
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
فلورا شور باي كالجاري بروبرتيز
Project number
3626
Site inspections
3

Schedule

Between February 2026 and July 2026 the site added about 0.5 points a month. At that rate it would finish around July 2042, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 July 2026

2.2%+2.2 pts

  • Flora Shore By Calgary Properties construction site, inspection photo 1, 8 July 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 2, 8 July 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 3, 8 July 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 4, 8 July 2026

26 February 2026

0%+0.0 pts

  • Flora Shore By Calgary Properties construction site, inspection photo 1, 26 February 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 2, 26 February 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 3, 26 February 2026
  • Flora Shore By Calgary Properties construction site, inspection photo 4, 26 February 2026

21 May 2025

0%

  • Flora Shore By Calgary Properties construction site, inspection photo 1, 21 May 2025
  • Flora Shore By Calgary Properties construction site, inspection photo 2, 21 May 2025

All 11 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Flora Shore By Calgary Properties?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Flora Shore By Calgary Properties handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2042. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Flora Shore By Calgary Properties?
Flora Shore By Calgary Properties was 2.2% built at the site inspection on 8 July 2026. The site has been inspected 3 times since May 2025. The Land Department took 11 site photos at its inspections.
Is Flora Shore By Calgary Properties delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Flora Shore By Calgary Properties?
The registered developer is Calgary Properties.
Which bank holds the escrow account for Flora Shore By Calgary Properties?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.