Flora Isle construction progress

The registered completion date for Flora Isle in Palm Deira is January 2028. At the last site inspection, in October 2026, it was 11% built. The developer is Flora Isle Real Estate Development.

11%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
January 2028
Finish at recent pace
May 2034
Construction started
December 2024
First registered
January 2025
Developer
Flora Isle Real Estate Development
Community
Palm Deira
Units
251
Escrow bank
Emirates Islamic Bank
Name in Arabic
فلورا ايل
Project number
3440
Site inspections
5

Schedule

Between April 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around May 2034, more than three months after its registered date of January 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

11%+4.1 pts

  • Flora Isle construction site, inspection photo 1, 20 October 2026
  • Flora Isle construction site, inspection photo 2, 20 October 2026
  • Flora Isle construction site, inspection photo 3, 20 October 2026
  • Flora Isle construction site, inspection photo 4, 20 October 2026

15 July 2026

7.2%+2.4 pts

  • Flora Isle construction site, inspection photo 1, 15 July 2026
  • Flora Isle construction site, inspection photo 2, 15 July 2026
  • Flora Isle construction site, inspection photo 3, 15 July 2026
  • Flora Isle construction site, inspection photo 4, 15 July 2026

3 April 2026

4.8%+2.5 pts

  • Flora Isle construction site, inspection photo 1, 3 April 2026
  • Flora Isle construction site, inspection photo 2, 3 April 2026
  • Flora Isle construction site, inspection photo 3, 3 April 2026
  • Flora Isle construction site, inspection photo 4, 3 April 2026

7 October 2025

2.4%+2.4 pts

  • Flora Isle construction site, inspection photo 1, 7 October 2025
  • Flora Isle construction site, inspection photo 2, 7 October 2025
  • Flora Isle construction site, inspection photo 3, 7 October 2025
  • Flora Isle construction site, inspection photo 4, 7 October 2025

4 December 2024

0%

  • Flora Isle construction site, inspection photo 1, 4 December 2024
  • Flora Isle construction site, inspection photo 2, 4 December 2024

All 24 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Flora Isle?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Flora Isle handover date?
The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Flora Isle?
Flora Isle was 11% built at the site inspection on 20 October 2026. The site has been inspected 5 times since December 2024. The Land Department took 24 site photos at its inspections.
Is Flora Isle delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Flora Isle?
The registered developer is Flora Isle Real Estate Development.
Which bank holds the escrow account for Flora Isle?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.