Do Residences construction progress

Do Residences in Palm Deira was registered to complete in December 2025 and is still under construction. At the last site inspection, in October 2026, it was 1.7% built. The developer is One International Real Estate Development.

1.7%

Built, at the site inspection of 2 October 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
January 2071
Construction started
June 2025
First registered
June 2025
Developer
One International Real Estate Development
Community
Palm Deira
Units
120
Escrow bank
First Abu Dhabi Bank
Name in Arabic
دو رسزيدينس
Project number
3804
Site inspections
2

Schedule

Do Residences was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around January 2071.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 October 2026

1.7%+0.9 pts

  • Do Residences construction site, inspection photo 1, 2 October 2026
  • Do Residences construction site, inspection photo 2, 2 October 2026
  • Do Residences construction site, inspection photo 3, 2 October 2026
  • Do Residences construction site, inspection photo 4, 2 October 2026

7 May 2026

0.8%

  • Do Residences construction site, inspection photo 1, 7 May 2026
  • Do Residences construction site, inspection photo 2, 7 May 2026
  • Do Residences construction site, inspection photo 3, 7 May 2026

All 8 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

One International Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Do Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Do Residences handover date?
The registered completion date was December 2025, and the register still lists Do Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2071. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Do Residences?
Do Residences was 1.7% built at the site inspection on 2 October 2026. The site has been inspected 2 times since May 2026. The Land Department took 8 site photos at its inspections.
Is Do Residences delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Do Residences?
The registered developer is One International Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Do Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.